22060 W INDEPENDENCIA ST 91364
Certificate Information: 22060 W INDEPENDENCIA ST 91364
- Application / Permit
- 25014-20000-01495
- Plan Check / Job No.
- B25VN09175
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING AND ENCLOSE PORTION OF FRONT PORCH TO BECOME PART OF SFD. REMODEL THROUGHOUT. ALL WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 7/23/2025
- Issuing Office
- Current Status
- CofO in Progress on 6/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2025 | MADISON ODELL |
| Corrections Issued | 4/9/2025 | MADISON ODELL |
| Applicant returned to address corrections | 4/21/2025 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/29/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 7/6/2025 | GURUNATH NESARAJAH |
| Issued | 7/23/2025 | APPLICANT |
| CofO in Progress | 6/4/2026 | JOHN HAYES |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/14/2025 | JEREMY CHOK |
| Grading Pre-Inspection | Cleared | 4/14/2025 | ROBERT PINA |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2025 | JEREMY CHOK |
| Specific Plan | Cleared | 7/1/2025 | TIFFANY CORRALES |
Contact Information
| Architect | Rieke,, Jonathan Eric; Lic. No.: NA39938 | , |
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/15/2025 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 8/15/2025 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 8/21/2025 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 9/29/2025 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/1/2025 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/3/2025 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 10/16/2025 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 10/16/2025 | Partial Approval | JOHN HAYES |
| Insulation | 10/20/2025 | Partial Approval | SCOTT SOBEL |
| BUILDING-Rough-Frame | 10/22/2025 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 10/22/2025 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 10/22/2025 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 11/6/2025 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Partial Approval | JEFFREY HARTLINE |
| Green Building Rough | 12/1/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Pre-Inspection | 12/1/2025 | Partial Approval | JEFFREY HARTLINE |
| Deputy Wood Construction | 12/8/2025 | Conditional Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 12/29/2025 | Corrections Issued | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2025 | Partial Approval | GEVORK IPCHYAN |
| Green Building Rough | 12/29/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Rough | 12/29/2025 | Partial Approval | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 1/8/2026 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 1/8/2026 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 1/8/2026 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 1/8/2026 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 1/15/2026 | Approved | SEAN WIRCH |
| HVAC-Rough | 1/15/2026 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 1/20/2026 | Approved | SEAN WIRCH |
| Green Building Rough | 1/20/2026 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 1/20/2026 | Partial Approval | SEAN WIRCH |
| Shower Pan | 1/20/2026 | Approved | SEAN WIRCH |
| Insulation | 1/30/2026 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 1/30/2026 | Approved | SEAN WIRCH |
| Drywall Nailing | 2/6/2026 | Approved | DAVID FASTIGGI |
| ELECTRICAL-Final | 5/5/2026 | Partial Approval | JOHN HAYES |
| Final | 5/28/2026 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 5/28/2026 | Approved | JOHN HAYES |
| Green Building Final | 5/28/2026 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/28/2026 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 5/28/2026 | Approved | JOHN HAYES |
| Final | 6/4/2026 | OK to Issue CofO | JOHN HAYES |