22060 W INDEPENDENCIA ST 91364

Certificate Information: 22060 W INDEPENDENCIA ST 91364

Application / Permit
25014-20000-01495
Plan Check / Job No.
B25VN09175
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING AND ENCLOSE PORTION OF FRONT PORCH TO BECOME PART OF SFD. REMODEL THROUGHOUT. ALL WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 7/23/2025
Issuing Office
Current Status
CofO in Progress on 6/4/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/4/2025 APPLICANT
Assigned to Plan Check Engineer 4/8/2025 MADISON ODELL
Corrections Issued 4/9/2025 MADISON ODELL
Applicant returned to address corrections 4/21/2025 GURUNATH NESARAJAH
Applicant returned to address corrections 4/29/2025 GURUNATH NESARAJAH
Plan Check Approved 7/6/2025 GURUNATH NESARAJAH
Issued 7/23/2025 APPLICANT
CofO in Progress 6/4/2026 JOHN HAYES

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/14/2025 JEREMY CHOK
Grading Pre-Inspection Cleared 4/14/2025 ROBERT PINA
Eng Process Fee Ord 176,300 Cleared 4/15/2025 JEREMY CHOK
Specific Plan Cleared 7/1/2025 TIFFANY CORRALES

Contact Information

Architect Rieke,, Jonathan Eric; Lic. No.: NA39938       ,
Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/15/2025 Partial Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/15/2025 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/21/2025 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 9/29/2025 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 10/1/2025 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 10/3/2025 Approved JOHN HAYES
BUILDING-Rough-Frame 10/16/2025 Partial Approval JOHN HAYES
PLUMBING-Rough 10/16/2025 Partial Approval JOHN HAYES
Insulation 10/20/2025 Partial Approval SCOTT SOBEL
BUILDING-Rough-Frame 10/22/2025 Not Ready for Inspection JOHN HAYES
Green Building Rough 10/22/2025 Not Ready for Inspection JOHN HAYES
Pre-Inspection 10/22/2025 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 11/6/2025 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/1/2025 Partial Approval JEFFREY HARTLINE
Green Building Rough 12/1/2025 Not Ready for Inspection JEFFREY HARTLINE
Pre-Inspection 12/1/2025 Partial Approval JEFFREY HARTLINE
Deputy Wood Construction 12/8/2025 Conditional Approval JOHN HAYES
BUILDING-Rough-Frame 12/29/2025 Corrections Issued GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/29/2025 Partial Approval GEVORK IPCHYAN
Green Building Rough 12/29/2025 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 12/29/2025 Partial Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 1/8/2026 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 1/8/2026 Not Ready for Inspection JOHN HAYES
Green Building Rough 1/8/2026 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 1/8/2026 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 1/15/2026 Approved SEAN WIRCH
HVAC-Rough 1/15/2026 Approved SEAN WIRCH
BUILDING-Rough-Frame 1/20/2026 Approved SEAN WIRCH
Green Building Rough 1/20/2026 Approved SEAN WIRCH
Interior/Exterior Lathing 1/20/2026 Partial Approval SEAN WIRCH
Shower Pan 1/20/2026 Approved SEAN WIRCH
Insulation 1/30/2026 Approved SEAN WIRCH
Interior/Exterior Lathing 1/30/2026 Approved SEAN WIRCH
Drywall Nailing 2/6/2026 Approved DAVID FASTIGGI
ELECTRICAL-Final 5/5/2026 Partial Approval JOHN HAYES
Final 5/28/2026 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 5/28/2026 Approved JOHN HAYES
Green Building Final 5/28/2026 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/28/2026 SGSOV Approved JOHN HAYES
Smoke Detectors 5/28/2026 Approved JOHN HAYES
Final 6/4/2026 OK to Issue CofO JOHN HAYES