20231 W MOBILE ST 91306
Certificate Information: 20231 W MOBILE ST 91306
- Application / Permit
- 25014-20000-01480
- Plan Check / Job No.
- B25VN09158
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION 165 S. F. TO THE MAIN HOUSE AND REMODEL THE KITCHEN
- Permit Issued
- Issued on 4/23/2025
- Issuing Office
- Current Status
- CofO in Progress on 6/1/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2025 | JOHN MESIAS |
| Corrections Issued | 4/4/2025 | JOHN MESIAS |
| Applicant returned to address corrections | 4/15/2025 | JOHN MESIAS |
| Plan Check Approved | 4/21/2025 | TSE MING HUANG |
| Issued | 4/23/2025 | APPLICANT |
| CofO in Progress | 4/21/2026 | ALEXANDER HANDY |
| No Progress | 6/1/2026 | ROBERT GOLD |
| CofO in Progress | 6/1/2026 | ROBERT GOLD |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/12/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2025 | SAFA JAVANMARDI |
| ZI | Cleared | 4/18/2025 | JAZMIN ROQUE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/2/2026 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 2/3/2026 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 2/3/2026 | Corrections Issued | HENRY KIM |
| Deputy Drilled-In Anchors | 2/18/2026 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 2/18/2026 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 2/25/2026 | Corrections Issued | DAVID FASTIGGI |
| ELECTRICAL-Rough | 2/25/2026 | Corrections Issued | DAVID FASTIGGI |
| PLUMBING-Rough | 2/25/2026 | Corrections Issued | DAVID FASTIGGI |
| BUILDING-Rough-Frame | 3/2/2026 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 3/2/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 3/2/2026 | Approved | ALEXANDER HANDY |
| Insulation | 3/11/2026 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 3/11/2026 | Partial Approval | ALEXANDER HANDY |
| Drywall Nailing | 3/16/2026 | Approved | DAVID FASTIGGI |
| ELECTRICAL-Final | 4/20/2026 | Approved | ALEXANDER HANDY |
| Final | 4/20/2026 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 4/20/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 4/20/2026 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/20/2026 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 4/20/2026 | Approved | ALEXANDER HANDY |