13878-13880 N FENTON AVE 91342
Certificate Information: 13878-13880 N FENTON AVE 91342
- Application / Permit
- 25014-20000-01472
- Plan Check / Job No.
- B25VN09127
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL TO SFD WITH ADDITION OF REAR ATTACHED PATIO, FRONT COVERED PORCH, AND CONVERSION OF (E) ATTACHED GARAGE INTO A JUNIOR ACCESSORY DWELLING UNIT TO COMPLY WITH GC 66323(a)(1) AND 66333
- Permit Issued
- Issued on 5/8/2025
- Issuing Office
- Current Status
- Issued on 5/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | ALFRED RAMIREZ |
| Corrections Issued | 4/22/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 4/24/2025 | STEVEN KIM |
| Building Plans Picked Up | 4/30/2025 | APPLICANT |
| Plan Check Approved | 5/8/2025 | ALFRED RAMIREZ |
| Issued | 5/8/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/25/2025 | BRYAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 4/25/2025 | BRYAN GODINEZ |
| Sewer availability | Cleared | 4/25/2025 | BRYAN GODINEZ |
| Miscellaneous | Cleared | 4/30/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2025 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/15/2025 | Partial Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/28/2025 | Partial Approval | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 5/30/2025 | Partial Approval | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 6/18/2025 | Partial Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/27/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 6/27/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 6/27/2025 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 7/2/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 7/2/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 7/15/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 7/15/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 7/15/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 7/21/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 6/22/2026 | Approved | KEVIN BERBERYAN |
| Final | 6/22/2026 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 6/22/2026 | Approved | KEVIN BERBERYAN |
| Green Building Final | 6/22/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Final | 6/22/2026 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 6/22/2026 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/22/2026 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 6/22/2026 | Approved | KEVIN BERBERYAN |