10017 N LANGDON AVE 91345
Certificate Information: 10017 N LANGDON AVE 91345
- Application / Permit
- 25014-20000-01463
- Plan Check / Job No.
- B25VN09054
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: ADDITION AND REMODEL TO (E) SFD. ALL WORK DONE PER ENGINEERING
- Permit Issued
- Issued on 4/21/2025
- Issuing Office
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2025 | GURUNATH NESARAJAH |
| Corrections Issued | 4/10/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 4/21/2025 | GURUNATH NESARAJAH |
| Issued | 4/21/2025 | APPLICANT |
| CofO in Progress | 8/11/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
| CofO Issued | 9/4/2025 | RUBEN SALAS |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/15/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 4/16/2025 | RYAN CASTRO |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/20/2025 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 5/20/2025 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 6/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 6/4/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 6/23/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 6/23/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 6/23/2025 | Approved | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 6/23/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/26/2025 | Approved | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 6/26/2025 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/1/2025 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 7/2/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 7/8/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/8/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 7/8/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/31/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/31/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/31/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 7/31/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/31/2025 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 7/31/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/31/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/31/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/6/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 8/6/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Smoke Detectors | 8/6/2025 | Approved | CHRISTOPHER ROJAS |