4319 N MANSON AVE 91364

Certificate Information: 4319 N MANSON AVE 91364

Application / Permit
25014-20000-01460
Plan Check / Job No.
B25VN09038
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD TO CREATE A BEDROOM
Permit Issued
Issued on 10/4/2025
Issuing Office
Current Status
CofO in Progress on 2/25/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/3/2025 APPLICANT
Assigned to Plan Check Engineer 4/8/2025 KAMYAR EMAMI
Corrections Issued 4/9/2025 KAMYAR EMAMI
Applicant returned to address corrections 8/13/2025 MOHAMMAD ESMAILI
Plan Check Approved 8/26/2025 MOHAMMAD ESMAILI
Issued 10/4/2025 APPLICANT
CofO in Progress 2/25/2026 JOHN HAYES

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/26/2025 MICHAEL TEMPLE
Roof/Waste drainage to street Cleared 6/26/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/22/2025 BIAINA HARITUNIAN
Sewer availability Cleared 8/22/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Golabtounkar,, Tony Hamid; Lic. No.: C49104 1434 WESTWOOD BLVD ST 17      LOS ANGELES, CA 90024

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/14/2025 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 10/16/2025 Partial Inspection JOHN KIDWELL
Pre-Inspection 10/16/2025 Partial Inspection JOHN KIDWELL
Footing/Foundation/Slab 10/17/2025 Conditional Approval JOHN KIDWELL
BUILDING-Rough-Frame 12/2/2025 Partial Approval JOHN HAYES
ELECTRICAL-Rough 12/2/2025 Not Ready for Inspection JOHN HAYES
Green Building Rough 12/2/2025 Not Ready for Inspection JOHN HAYES
HVAC-Rough 12/2/2025 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 12/2/2025 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 12/4/2025 Partial Approval JOHN HAYES
ELECTRICAL-Rough 12/4/2025 Not Ready for Inspection JOHN HAYES
Green Building Rough 12/4/2025 Not Ready for Inspection JOHN HAYES
HVAC-Rough 12/4/2025 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 12/4/2025 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 12/4/2025 Corrections Issued JOHN HAYES
Deputy Wood Construction 12/5/2025 Conditional Approval JOHN HAYES
BUILDING-Rough-Frame 12/8/2025 Approved JOHN HAYES
Green Building Rough 12/8/2025 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 12/8/2025 Approved JOHN HAYES
Interior/Exterior Lathing 12/11/2025 Partial Approval JOHN HAYES
Insulation 12/15/2025 Approved JOHN HAYES
Drywall Nailing 12/18/2025 Approved JOHN HAYES
ELECTRICAL-Final 1/21/2026 Approved JOHN HAYES
Final 1/21/2026 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 1/21/2026 Approved JOHN HAYES
Green Building Final 1/21/2026 Approved JOHN HAYES
HVAC-Final 1/21/2026 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 1/21/2026 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/21/2026 SGSOV Not Ready JOHN HAYES
Smoke Detectors 1/21/2026 Approved JOHN HAYES
Final 2/25/2026 OK to Issue CofO JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/25/2026 SGSOV Approved JOHN HAYES
Service/Power Release 2/25/2026 Approved JOHN HAYES