17449 W KESWICK ST 91325

Certificate Information: 17449 W KESWICK ST 91325

Application / Permit
25014-20000-01449
Plan Check / Job No.
B25VN08971
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD TO CREATE A NEW BATHROOM
Permit Issued
Issued on 5/10/2025
Issuing Office
Current Status
CofO Issued on 12/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2025 APPLICANT
Assigned to Plan Check Engineer 4/8/2025 KAMYAR EMAMI
Corrections Issued 4/9/2025 KAMYAR EMAMI
Applicant returned to address corrections 5/5/2025 GIOVANNY CHAVEZ
Plan Check Approved 5/10/2025 GIOVANNY CHAVEZ
Issued 5/10/2025 APPLICANT
CofO in Progress 11/19/2025 GAREN HAYRAPETYAN
Permit Finaled 12/9/2025 RUBEN SALAS
CofO Issued 12/9/2025 RUBEN SALAS
Permit Finaled 12/9/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/26/2025 BRYAN GODINEZ
Sewer availability Cleared 4/26/2025 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/7/2025 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/17/2025 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 6/25/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 7/3/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/25/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 7/25/2025 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 7/25/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 7/25/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 7/25/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/31/2025 Partial Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 7/31/2025 Partial Approval SALVADOR MARTINEZ
Green Building Rough 7/31/2025 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 7/31/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 7/31/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 8/13/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 8/20/2025 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 8/20/2025 Approved JOAQUIN GREENOUGH
Shower Pan 8/20/2025 Approved JOAQUIN GREENOUGH
Insulation 8/26/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 8/26/2025 Approved LOUIS ESCOTO
Drywall Nailing 9/3/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 9/3/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/5/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 11/5/2025 Approved GAREN HAYRAPETYAN
Final 11/5/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 11/5/2025 Approved GAREN HAYRAPETYAN
Smoke Detectors 11/5/2025 Approved GAREN HAYRAPETYAN
Final 11/19/2025 OK to Issue CofO GAREN HAYRAPETYAN