7856-7858 N SEDAN AVE 91304
Certificate Information: 7856-7858 N SEDAN AVE 91304
- Application / Permit
- 25014-20000-01447
- Plan Check / Job No.
- B25VN08951
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN CONVERT ATTACHED GARAGE TO ADU PER LAMC 12.22 A.33 (c) and (e) WITH NEW FRONT AND REAR IRREGULAR SHAPED ADDITION TO SINGLE-FAMILY DWELLING WITH INTERIOR REMODEL. ALL WORK PER ENGINEER. NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 6/23/2025
- Issuing Office
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2025 | ALEC MOUSAKHANIAN |
| Corrections Issued | 4/25/2025 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 6/3/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 6/10/2025 | ALEC MOUSAKHANIAN |
| Issued | 6/23/2025 | APPLICANT |
| CofO in Progress | 1/9/2026 | JEFFREY HARTLINE |
| Permit Finaled | 1/21/2026 | JOHN JANSON |
| CofO Issued | 1/21/2026 | JOHN JANSON |
| Permit Finaled | 1/21/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/10/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/10/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | H & M Development And Construction Corp; Lic. No.: 990630-B | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/26/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 7/3/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/10/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2025 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 8/19/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 8/19/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 8/19/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 8/19/2025 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 8/19/2025 | Approved | JEFFREY HARTLINE |
| Wood Frame | 8/19/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 8/22/2025 | Partial Approval | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 8/27/2025 | Partial Approval | JEFFREY HARTLINE |
| Shower Pan | 8/27/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 9/2/2025 | Approved | JEFFREY HARTLINE |
| Special/Order Compliance | 10/16/2025 | Corrections Issued | JEFFREY HARTLINE |
| ELECTRICAL-Final | 12/4/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 12/4/2025 | Corrections Issued | JEFFREY HARTLINE |
| HVAC-Final | 12/4/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 12/4/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/4/2025 | SGSOV Not Ready | JEFFREY HARTLINE |
| Service/Power Release | 12/4/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 12/4/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Final | 12/24/2025 | No Access for Inspection | JEFFREY HARTLINE |
| Final | 12/24/2025 | Corrections Issued | JEFFREY HARTLINE |
| HVAC-Final | 12/24/2025 | No Access for Inspection | JEFFREY HARTLINE |
| PLUMBING-Final | 12/24/2025 | No Access for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/24/2025 | SGSOV Not Ready | JEFFREY HARTLINE |
| Smoke Detectors | 12/24/2025 | No Access for Inspection | JEFFREY HARTLINE |
| Final | 12/29/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/29/2025 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 12/29/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 1/9/2026 | Approved | JEFFREY HARTLINE |
| Final | 1/9/2026 | OK to Issue CofO | JEFFREY HARTLINE |
| PLUMBING-Final | 1/9/2026 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 1/9/2026 | Approved | JEFFREY HARTLINE |