7856-7858 N SEDAN AVE 91304

Certificate Information: 7856-7858 N SEDAN AVE 91304

Application / Permit
25014-20000-01447
Plan Check / Job No.
B25VN08951
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN CONVERT ATTACHED GARAGE TO ADU PER LAMC 12.22 A.33 (c) and (e) WITH NEW FRONT AND REAR IRREGULAR SHAPED ADDITION TO SINGLE-FAMILY DWELLING WITH INTERIOR REMODEL. ALL WORK PER ENGINEER. NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
Permit Issued
Issued on 6/23/2025
Issuing Office
Current Status
CofO Issued on 1/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2025 APPLICANT
Assigned to Plan Check Engineer 4/24/2025 ALEC MOUSAKHANIAN
Corrections Issued 4/25/2025 ALEC MOUSAKHANIAN
Applicant returned to address corrections 6/3/2025 ALEC MOUSAKHANIAN
Plan Check Approved 6/10/2025 ALEC MOUSAKHANIAN
Issued 6/23/2025 APPLICANT
CofO in Progress 1/9/2026 JEFFREY HARTLINE
Permit Finaled 1/21/2026 JOHN JANSON
CofO Issued 1/21/2026 JOHN JANSON
Permit Finaled 1/21/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/10/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/10/2025 BIAINA HARITUNIAN
Sewer availability Cleared 5/10/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/13/2025 BIAINA HARITUNIAN

Contact Information

Contractor H & M Development And Construction Corp; Lic. No.: 990630-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/26/2025 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 7/3/2025 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/10/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 8/19/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 8/19/2025 Approved JEFFREY HARTLINE
HVAC-Rough 8/19/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 8/19/2025 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 8/19/2025 Approved JEFFREY HARTLINE
Wood Frame 8/19/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 8/22/2025 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 8/27/2025 Partial Approval JEFFREY HARTLINE
Shower Pan 8/27/2025 Approved JEFFREY HARTLINE
Drywall Nailing 9/2/2025 Approved JEFFREY HARTLINE
Special/Order Compliance 10/16/2025 Corrections Issued JEFFREY HARTLINE
ELECTRICAL-Final 12/4/2025 Not Ready for Inspection JEFFREY HARTLINE
Final 12/4/2025 Corrections Issued JEFFREY HARTLINE
HVAC-Final 12/4/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 12/4/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Not Ready JEFFREY HARTLINE
Service/Power Release 12/4/2025 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 12/4/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Final 12/24/2025 No Access for Inspection JEFFREY HARTLINE
Final 12/24/2025 Corrections Issued JEFFREY HARTLINE
HVAC-Final 12/24/2025 No Access for Inspection JEFFREY HARTLINE
PLUMBING-Final 12/24/2025 No Access for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 12/24/2025 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 12/24/2025 No Access for Inspection JEFFREY HARTLINE
Final 12/29/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 12/29/2025 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 12/29/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 1/9/2026 Approved JEFFREY HARTLINE
Final 1/9/2026 OK to Issue CofO JEFFREY HARTLINE
PLUMBING-Final 1/9/2026 Approved JEFFREY HARTLINE
Service/Power Release 1/9/2026 Approved JEFFREY HARTLINE