2921 S CHESAPEAKE AVE 90016
Certificate Information: 2921 S CHESAPEAKE AVE 90016
- Application / Permit
- 25014-20000-01440
- Plan Check / Job No.
- B25VN08922
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL WITH (N) FIRST STORY ADDITION OF IRREGULAR SHAPE (39'-9" x 33'-11") AND SECOUND STORY ADDITION OF 606 SQFT IRREGULAR SHAPE. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 8/1/2025
- Issuing Office
- Metro
- Current Status
- Issued on 8/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | EDWARD MEHRABIAN |
| Corrections Issued | 4/24/2025 | EDWARD MEHRABIAN |
| Quality Review Completed | 4/29/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 5/8/2025 | APPLICANT |
| Plan Check Approved | 5/28/2025 | EDWARD MEHRABIAN |
| Issued | 8/1/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2025 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 5/9/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 5/9/2025 | JESSICA OPINION |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/25/2025 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Partial Approval | JUSTIN HAWLEY |
| Deputy Wood Construction | 10/8/2025 | Conditional Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 10/8/2025 | Corrections Issued | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2025 | Corrections Issued | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2025 | Corrections Issued | JUSTIN HAWLEY |
| Underground Mechanical | 12/12/2025 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Corrections Issued | JUSTIN HAWLEY |
| PLUMBING-Rough | 12/22/2025 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/28/2026 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 1/28/2026 | Approved | JEFFREY MEAD |
| Green Building Rough | 1/28/2026 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 1/28/2026 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 1/28/2026 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/30/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/4/2026 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 2/4/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Rough | 2/13/2026 | Approved | JUSTIN HAWLEY |
| Insulation | 2/13/2026 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 2/13/2026 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 2/19/2026 | Approved | JUSTIN HAWLEY |
| Shower Pan | 2/19/2026 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 2/25/2026 | Approved | JUSTIN HAWLEY |
| Final | 5/29/2026 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 5/29/2026 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 5/29/2026 | Approved | JUSTIN HAWLEY |