4312-4314 N EMPRESS AVE 91436
Certificate Information: 4312-4314 N EMPRESS AVE 91436
- Application / Permit
- 25014-20000-01431
- Plan Check / Job No.
- B25VN08884
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ADDITION TO (E) SFD TO CREATE SECOUND STORY (32'-2" x 23'-6" ) ADU ABOVE GARAGE PER LAMC 12.22 A.33 (c) and (e)
- Permit Issued
- Issued on 6/12/2025
- Issuing Office
- Current Status
- Issued on 6/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2025 | EDWARD MEHRABIAN |
| Corrections Issued | 4/8/2025 | EDWARD MEHRABIAN |
| Quality Review Completed | 4/17/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 4/21/2025 | APPLICANT |
| Applicant returned to address corrections | 5/23/2025 | EDWARD MEHRABIAN |
| Plan Check Approved | 6/12/2025 | EDWARD MEHRABIAN |
| Issued | 6/12/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2025 | BIAINA HARITUNIAN |
| BHO/Hillside ordinance | Cleared | 4/18/2025 | BIAINA HARITUNIAN |
| BHO/Hillside ordinance | Cleared | 4/18/2025 | BIAINA HARITUNIAN |
| BHO/Hillside ordinance | Cleared | 4/18/2025 | BIAINA HARITUNIAN |
| BHO/Hillside ordinance | Cleared | 4/18/2025 | BIAINA HARITUNIAN |
| BHO/Hillside ordinance | Cleared | 4/18/2025 | BIAINA HARITUNIAN |
| Miscellaneous | Cleared | 4/18/2025 | JASON CHAN |
| Grading Pre-Inspection | Cleared | 4/21/2025 | ROBERT PINA |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/29/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/29/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/29/2025 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 6/12/2025 | EDWARD MEHRABIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 7/24/2026 Time Frame: 10-12 |
Inspection Request History
| Deputy Drilled-In Anchors | 6/18/2025 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/20/2025 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/25/2025 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/30/2025 | Partial Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 7/2/2025 | Conditional Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 7/9/2025 | Corrections Issued | THOMAS FINNILA |
| Deputy Steel/Welding | 7/11/2025 | Partial Approval | SEAN WIRCH |
| Wood Frame | 7/14/2025 | Corrections Issued | THOMAS FINNILA |
| Deputy Steel/Welding | 7/15/2025 | Partial Approval | SEAN WIRCH |
| Deputy Steel/Welding | 7/30/2025 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/15/2025 | Approved | JOHN KIDWELL |
| HVAC-Rough | 10/16/2025 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 10/16/2025 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 11/14/2025 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/19/2025 | Approved | SEAN WIRCH |
| Insulation | 12/3/2025 | Conditional Approval | THOMAS FINNILA |
| Shower Pan | 12/3/2025 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/15/2025 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/11/2026 | Approved | THOMAS FINNILA |
| Drywall Nailing | 2/11/2026 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/11/2026 | Approved | THOMAS FINNILA |
| Green Building Rough | 2/11/2026 | Approved | THOMAS FINNILA |
| HVAC-Rough | 2/11/2026 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 2/11/2026 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 6/4/2026 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 6/4/2026 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 6/23/2026 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/23/2026 | Approved | THOMAS FINNILA |
| HVAC-Final | 6/23/2026 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 6/26/2026 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 6/26/2026 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 7/6/2026 | Approved | THOMAS FINNILA |
| HVAC-Final | 7/6/2026 | Approved | THOMAS FINNILA |
| Special/Order Compliance | 7/16/2026 | Corrections Issued | THOMAS FINNILA |