14956 W SEPTO ST 91345

Certificate Information: 14956 W SEPTO ST 91345

Application / Permit
25014-20000-01397
Plan Check / Job No.
B25VN08645
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Detached 1-story garage conversion to ADU w/addition per LAMC 12.22 A.33(b),(1),(c),(d),(h) and (k)
Permit Issued
Issued on 4/18/2025
Issuing Office
Current Status
CofO Issued on 1/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2025 APPLICANT
Assigned to Plan Check Engineer 4/4/2025 DAVID CASTILLO
Corrections Issued 4/6/2025 DAVID CASTILLO
Plan Check Approved 4/17/2025 ZAW HAN
Issued 4/18/2025 APPLICANT
CofO in Progress 1/2/2026 JENNIFER RABUCHIN
Permit Finaled 1/9/2026 RUBEN SALAS
CofO Issued 1/9/2026 RUBEN SALAS
Permit Finaled 1/9/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/12/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 4/12/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 4/14/2025 SAFA JAVANMARDI
Sewer availability Cleared 4/14/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/12/2025 Corrections Issued JENNIFER RABUCHIN
Pre-Inspection 6/12/2025 Partial Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 6/17/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 6/17/2025 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 6/30/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 6/30/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 7/2/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 7/24/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 7/24/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 7/24/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 7/24/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/28/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/30/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 7/31/2025 Corrections Issued JENNIFER RABUCHIN
Insulation 7/31/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/7/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/7/2025 Approved JENNIFER RABUCHIN
Shower Pan 8/7/2025 Approved JENNIFER RABUCHIN
Sewer 10/10/2025 Corrections Issued JENNIFER RABUCHIN
Sewer 10/22/2025 Partial Approval JENNIFER RABUCHIN
Gas Test 11/3/2025 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 11/3/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/9/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/9/2025 Corrections Issued JENNIFER RABUCHIN
Final 12/9/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 12/9/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 12/9/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 12/9/2025 Approved JENNIFER RABUCHIN
Final 12/12/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 12/12/2025 Approved JENNIFER RABUCHIN