23113-23115 W SCHOOLCRAFT ST 91307

Certificate Information: 23113-23115 W SCHOOLCRAFT ST 91307

Application / Permit
25014-20000-01365
Plan Check / Job No.
B25VN08420
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: ADDITION 10'-4" X 6'-6" TO THE S.F.D. AND CONVERT THE (E) GARAGE INTO JUNIOR ACCESSORY DWELLING UNIT PER GC 66323(a)(1) and 66333. ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/6/2025
Issuing Office
Current Status
CofO Issued on 10/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2025 APPLICANT
Assigned to Plan Check Engineer 4/2/2025 ARAMIK SHAHMIRZAIAN
Corrections Issued 4/2/2025 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 4/16/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 4/21/2025 ARAMIK SHAHMIRZAIAN
Issued 5/6/2025 APPLICANT
CofO in Progress 10/24/2025 GEVORK IPCHYAN
Permit Finaled 10/27/2025 JOHN JANSON
CofO Issued 10/27/2025 JOHN JANSON
Permit Finaled 10/27/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/7/2025 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/7/2025 JEANIE LAM
Roof/Waste drainage to street Cleared 4/7/2025 JEANIE LAM
Sewer availability Cleared 4/7/2025 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/9/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 5/9/2025 Partial Approval GEVORK IPCHYAN
PLUMBING-Rough 5/27/2025 Partial Approval GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Partial Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 6/17/2025 Partial Approval GEVORK IPCHYAN
Rough-Elec/Plmb/HVAC 6/17/2025 Approved GEVORK IPCHYAN
Wood Frame 6/17/2025 Partial Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 6/26/2025 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/26/2025 Partial Approval GEVORK IPCHYAN
Green Building Rough 6/26/2025 Approved GEVORK IPCHYAN
Insulation 6/26/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 6/26/2025 Approved GEVORK IPCHYAN
Drywall Nailing 7/7/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 7/7/2025 Not Ready for Inspection GEVORK IPCHYAN
Interior/Exterior Lathing 7/30/2025 Partial Approval GEVORK IPCHYAN
Sewer 9/3/2025 Approved GEVORK IPCHYAN
Final 10/21/2025 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Not Ready GEVORK IPCHYAN
Smoke Detectors 10/21/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Final 10/24/2025 Approved GEVORK IPCHYAN
Final 10/24/2025 OK to Issue CofO GEVORK IPCHYAN
HVAC-Final 10/24/2025 Approved GEVORK IPCHYAN
PLUMBING-Final 10/24/2025 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Approved GEVORK IPCHYAN