10007 N BURNET AVE 91345
Certificate Information: 10007 N BURNET AVE 91345
- Application / Permit
- 25014-20000-01360
- Plan Check / Job No.
- B25VN08395
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EX. SINGLE FAMILY DWELLING FOR NEW FAMILY ROOM, BEDROOM AND BATHROOM.
- Permit Issued
- Issued on 10/14/2025
- Issuing Office
- Valley
- Current Status
- Issued on 10/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 3/27/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 5/27/2025 | ROSENDO MEDINA |
| Plan Check Approved | 5/27/2025 | ROSENDO MEDINA |
| Issued | 10/14/2025 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/20/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/20/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/22/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Nork Construction Inc; Lic. No.: 1058592-B | 835 E HARVARD RD BURBANK, CA 91501 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/17/2025 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 10/17/2025 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 10/21/2025 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 10/22/2025 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/12/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 11/12/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/12/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/9/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/9/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 12/9/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 12/9/2025 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/16/2025 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 12/24/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 12/24/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/29/2025 | Partial Inspection | LOUIS ESCOTO |
| Green Building Rough | 12/29/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 1/16/2026 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/21/2026 | Approved | JENNIFER RABUCHIN |