2615 S HOLT AVE 90034

Certificate Information: 2615 S HOLT AVE 90034

Application / Permit
25014-20000-01339
Plan Check / Job No.
B25VN08215
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING TO ADD A NEW BATHROOM AND CLOSET. REMODEL OF THE KITCHEN. ALL WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 4/21/2025
Issuing Office
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2025 APPLICANT
Assigned to Plan Check Engineer 3/26/2025 MIROOSH KHACHATOORIAN
Corrections Issued 3/26/2025 MIROOSH KHACHATOORIAN
Issued 4/21/2025 APPLICANT
CofO in Progress 9/11/2025 EVAN COOPER
Permit Finaled 9/18/2025 RICHARD STEINBACH
CofO Issued 9/18/2025 RICHARD STEINBACH
Permit Finaled 9/18/2025 RICHARD STEINBACH

Permit Application Clearance Information

ZA Case Cleared 4/4/2025 DALIA MOKAYED
Roof/Waste drainage to street Cleared 4/10/2025 LEE GUILBEAUX
Sewer availability Cleared 4/10/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/10/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/14/2025 LEE GUILBEAUX

Contact Information

Contractor Cali Builders & Construction Inc; Lic. No.: 1051566-B 15130 VENTURA BLVD STE 250      SHERMAN OAKS, CA 91403
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/1/2025 Corrections Issued MEL KHACHATOURIAN
Pre-Inspection 5/5/2025 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 5/8/2025 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 5/13/2025 Partial Approval EVAN COOPER
Footing/Foundation/Slab 5/13/2025 Approved EVAN COOPER
Insulation 5/13/2025 Partial Approval EVAN COOPER
ELECTRICAL-Rough 5/29/2025 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 5/29/2025 Corrections Issued ARAM AVEDISIAN
Wood Frame 5/29/2025 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 6/6/2025 Partial Approval EVAN COOPER
ELECTRICAL-Rough 6/6/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Partial Approval EVAN COOPER
HVAC-Rough 6/6/2025 Approved EVAN COOPER
PLUMBING-Rough 6/6/2025 Approved EVAN COOPER
Wood Frame 6/6/2025 Partial Approval EVAN COOPER
Interior/Exterior Lathing 6/11/2025 Partial Approval EVAN COOPER
Shower Pan 6/11/2025 Approved EVAN COOPER
Insulation 6/16/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 6/20/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 9/9/2025 Approved EVAN COOPER
ELECTRICAL-Final 9/9/2025 Approved EVAN COOPER
Final 9/9/2025 Corrections Issued EVAN COOPER
Green Building Final 9/9/2025 Approved EVAN COOPER
Green Building Rough 9/9/2025 Approved EVAN COOPER
HVAC-Final 9/9/2025 Approved EVAN COOPER
MERV13>=Final 9/9/2025 Approved EVAN COOPER
MERV13>=Rough 9/9/2025 Approved EVAN COOPER
PLUMBING-Final 9/9/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Not Ready EVAN COOPER
Smoke Detectors 9/9/2025 Approved EVAN COOPER
Final 9/11/2025 OK to Issue CofO EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/11/2025 SGSOV Approved EVAN COOPER