516 S NORTON AVE 90020

Certificate Information: 516 S NORTON AVE 90020

Application / Permit
25014-20000-01329
Plan Check / Job No.
B25VN08151
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 10'-11" X 13'-8" 2ND FLOOR ADDITION TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/25/2025
Issuing Office
Current Status
Issued on 6/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/25/2025 APPLICANT
Assigned to Plan Check Engineer 3/27/2025 RAPHAEL ROSAS
Corrections Issued 4/1/2025 RAPHAEL ROSAS
Quality Review Completed 4/1/2025 STEVEN KIM
Building Plans Picked Up 4/1/2025 APPLICANT
Plan Check Approved 6/25/2025 RAPHAEL ROSAS
Issued 6/25/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/25/2025 JEREMY CHOK
HPOZ Cleared 6/25/2025 DAMIAN GATTO
Miscellaneous Cleared 6/25/2025 DAMIAN GATTO
Roof/Waste drainage to street Cleared 6/25/2025 JEREMY CHOK
Sewer availability Cleared 6/25/2025 JEREMY CHOK
ZI Cleared 6/25/2025 DAMIAN GATTO

Contact Information

Contractor Mc Burney Matthew Construction; Lic. No.: 509046-B 21427 DE LA OSA STREET      WOODLAND HILLS, CA 91364
Engineer Peck,, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/21/2025 Approved JEFFREY MEAD
Footing/Foundation/Slab 8/21/2025 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 10/31/2025 Partial Approval RAUL BARAJAS
PLUMBING-Rough 10/31/2025 Partial Approval RAUL BARAJAS
Wood Frame 10/31/2025 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 11/18/2025 Not Ready for Inspection JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 11/18/2025 Partial Approval JEFFREY MEAD
HVAC-Rough 11/18/2025 Not Ready for Inspection JEFFREY MEAD
PLUMBING-Rough 11/18/2025 Corrections Issued JEFFREY MEAD
Wood Frame 12/22/2025 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Rough 12/23/2025 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Partial Approval JEFFREY MEAD
HVAC-Rough 12/23/2025 Corrections Issued JEFFREY MEAD
BUILDING-Rough-Frame 12/26/2025 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/26/2025 Approved FREDDIE RIVERA
Green Building Rough 12/26/2025 Approved FREDDIE RIVERA
Insulation 1/2/2026 Approved DAVID WILLIAMS
Drywall Nailing 1/20/2026 Approved ALEX COLIN
Shower Pan 1/22/2026 Approved JEFFREY MEAD
Interior/Exterior Lathing 1/29/2026 Approved JEFFREY MEAD