516 S NORTON AVE 90020
Certificate Information: 516 S NORTON AVE 90020
- Application / Permit
- 25014-20000-01329
- Plan Check / Job No.
- B25VN08151
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 10'-11" X 13'-8" 2ND FLOOR ADDITION TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/25/2025
- Issuing Office
- Current Status
- Issued on 6/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | RAPHAEL ROSAS |
| Corrections Issued | 4/1/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 4/1/2025 | STEVEN KIM |
| Building Plans Picked Up | 4/1/2025 | APPLICANT |
| Plan Check Approved | 6/25/2025 | RAPHAEL ROSAS |
| Issued | 6/25/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2025 | JEREMY CHOK |
| HPOZ | Cleared | 6/25/2025 | DAMIAN GATTO |
| Miscellaneous | Cleared | 6/25/2025 | DAMIAN GATTO |
| Roof/Waste drainage to street | Cleared | 6/25/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 6/25/2025 | JEREMY CHOK |
| ZI | Cleared | 6/25/2025 | DAMIAN GATTO |
Contact Information
| Contractor | Mc Burney Matthew Construction; Lic. No.: 509046-B | 21427 DE LA OSA STREET WOODLAND HILLS, CA 91364 |
| Engineer | Peck,, Christopher Mount; Lic. No.: C58162 | 25 SOUTH EL MOLINO AVE PASADENA, CA 911012023 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/21/2025 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 8/21/2025 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 10/31/2025 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 10/31/2025 | Partial Approval | RAUL BARAJAS |
| Wood Frame | 10/31/2025 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 11/18/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2025 | Partial Approval | JEFFREY MEAD |
| HVAC-Rough | 11/18/2025 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 11/18/2025 | Corrections Issued | JEFFREY MEAD |
| Wood Frame | 12/22/2025 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 12/23/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Partial Approval | JEFFREY MEAD |
| HVAC-Rough | 12/23/2025 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/26/2025 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2025 | Approved | FREDDIE RIVERA |
| Green Building Rough | 12/26/2025 | Approved | FREDDIE RIVERA |
| Insulation | 1/2/2026 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 1/20/2026 | Approved | ALEX COLIN |
| Shower Pan | 1/22/2026 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 1/29/2026 | Approved | JEFFREY MEAD |