19350 W WELBY WAY 91335
Certificate Information: 19350 W WELBY WAY 91335
- Application / Permit
- 25014-20000-01303
- Plan Check / Job No.
- B25VN07952
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Addition to and conversion of (E) detached storage to an ADU per LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 6/24/2025
- Issuing Office
- Current Status
- CofO in Progress on 2/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2025 | HOOMAN HAJIZADEH |
| Corrections Issued | 3/31/2025 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 5/22/2025 | CAROLEAN BASMA |
| Applicant returned to address corrections | 6/4/2025 | AMY GUEVARRA |
| Plan Check Approved | 6/23/2025 | DAVID CASTILLO |
| Issued | 6/24/2025 | APPLICANT |
| CofO in Progress | 2/3/2026 | ARUTYUN MADATYAN |
| CofO in Progress | 2/25/2026 | ROBERT GOLD |
Permit Application Clearance Information
| ZI | Cleared | 4/3/2025 | JASON CHAN |
| Address approval | Cleared | 4/5/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/5/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/5/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/7/2025 | LEE GUILBEAUX |
| Construction within easement | Cleared | 5/8/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/9/2025 | Corrections Issued | JEFFREY HARTLINE |
| Underground Mechanical | 7/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 8/25/2025 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 8/25/2025 | Partial Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 8/28/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 9/3/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 9/24/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2025 | Partial Approval | MORRIS JACKSON |
| HVAC-Rough | 9/24/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 9/24/2025 | Corrections Issued | MORRIS JACKSON |
| BUILDING-Rough-Frame | 10/8/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 10/8/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 10/8/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 10/15/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 10/15/2025 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 10/15/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 10/21/2025 | Approved | ARUTYUN MADATYAN |
| Final | 1/28/2026 | Corrections Issued | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 1/28/2026 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 2/2/2026 | Approved | ARUTYUN MADATYAN |
| Final | 2/2/2026 | Partial Approval | ARUTYUN MADATYAN |
| HVAC-Final | 2/2/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 2/2/2026 | Approved | ARUTYUN MADATYAN |
| Special/Order Compliance | 2/26/2026 | Corrections Issued | ARUTYUN MADATYAN |