19350 W WELBY WAY 91335

Certificate Information: 19350 W WELBY WAY 91335

Application / Permit
25014-20000-01303
Plan Check / Job No.
B25VN07952
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Addition to and conversion of (E) detached storage to an ADU per LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 6/24/2025
Issuing Office
Current Status
CofO in Progress on 2/3/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/26/2025 APPLICANT
Assigned to Plan Check Engineer 3/28/2025 HOOMAN HAJIZADEH
Corrections Issued 3/31/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 5/22/2025 CAROLEAN BASMA
Applicant returned to address corrections 6/4/2025 AMY GUEVARRA
Plan Check Approved 6/23/2025 DAVID CASTILLO
Issued 6/24/2025 APPLICANT
CofO in Progress 2/3/2026 ARUTYUN MADATYAN
CofO in Progress 2/25/2026 ROBERT GOLD

Permit Application Clearance Information

ZI Cleared 4/3/2025 JASON CHAN
Address approval Cleared 4/5/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/5/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/5/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/7/2025 LEE GUILBEAUX
Sewer availability Cleared 4/7/2025 LEE GUILBEAUX
Construction within easement Cleared 5/8/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Zohrevand,, Pedram; Lic. No.: C82328 19562 VENTURA BLVD UNIT 238      TARZANA, CA 91356

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/9/2025 Corrections Issued JEFFREY HARTLINE
Underground Mechanical 7/24/2025 Not Ready for Inspection ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 8/25/2025 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 8/25/2025 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 8/28/2025 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 9/3/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 9/24/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 9/24/2025 Partial Approval MORRIS JACKSON
HVAC-Rough 9/24/2025 Approved MORRIS JACKSON
PLUMBING-Rough 9/24/2025 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 10/8/2025 Approved ARUTYUN MADATYAN
Green Building Rough 10/8/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 10/8/2025 Approved ARUTYUN MADATYAN
Insulation 10/15/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 10/15/2025 Partial Approval ARUTYUN MADATYAN
Shower Pan 10/15/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 10/21/2025 Approved ARUTYUN MADATYAN
Final 1/28/2026 Corrections Issued ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 1/28/2026 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 1/28/2026 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 2/2/2026 Approved ARUTYUN MADATYAN
Final 2/2/2026 Partial Approval ARUTYUN MADATYAN
HVAC-Final 2/2/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 2/2/2026 Approved ARUTYUN MADATYAN
Special/Order Compliance 2/26/2026 Corrections Issued ARUTYUN MADATYAN