10529 W BASSETT ST 91405
Certificate Information: 10529 W BASSETT ST 91405
- Application / Permit
- 25014-20000-01284
- Plan Check / Job No.
- B25VN07828
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New second story ADU over existing detached garage.
- Permit Issued
- Issued on 5/14/2025
- Issuing Office
- Current Status
- CofO Issued on 5/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | JOE VO |
| Corrections Issued | 3/30/2025 | JOE VO |
| Quality Review Completed | 4/1/2025 | GARO TELMI |
| Plan Check Approved | 5/12/2025 | JOE VO |
| Issued | 5/14/2025 | APPLICANT |
| CofO in Progress | 5/18/2026 | VINCENT HANLEY |
| Permit Finaled | 5/29/2026 | RUBEN SALAS |
| CofO Issued | 5/29/2026 | RUBEN SALAS |
| Permit Finaled | 5/29/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 4/12/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 4/14/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Amelfig Builders & Remodeling Inc; Lic. No.: 1028969-B | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 6/5/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 6/5/2025 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 6/13/2025 | Approved | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 6/13/2025 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 6/13/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 7/8/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 7/8/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 7/8/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 7/8/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 7/8/2025 | Approved | RYAN SALAZAR |
| Wood Frame | 7/8/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/9/2025 | Approved | DAVID ANDERSON |
| Insulation | 7/9/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/9/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Shower Pan | 7/10/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/14/2025 | Approved | RYAN SALAZAR |
| Insulation | 7/14/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/14/2025 | Approved | RYAN SALAZAR |
| Final | 12/23/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 12/23/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Not Required | RYAN SALAZAR |
| Smoke Detectors | 12/23/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 5/14/2026 | Approved | VINCENT HANLEY |
| Final | 5/14/2026 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 5/14/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/14/2026 | Approved | VINCENT HANLEY |