7942 N SANGAMON AVE 91352

Certificate Information: 7942 N SANGAMON AVE 91352

Application / Permit
25014-20000-01279
Plan Check / Job No.
B25VN07821
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN EXISTING HOUSE REMODELING, 1ST FLOOR ADDITION, NEW SECOND FLOOR
Permit Issued
Issued on 6/7/2025
Issuing Office
Current Status
CofO Issued on 2/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2025 APPLICANT
Assigned to Plan Check Engineer 4/3/2025 ARSALAN SHABESTARI
Corrections Issued 4/10/2025 ARSALAN SHABESTARI
Quality Review Completed 4/16/2025 PRANITA SHAH
Plan Check Approved 6/6/2025 ARSALAN SHABESTARI
Issued 6/7/2025 APPLICANT
CofO in Progress 12/22/2025 DAVID ANDERSON
Permit Finaled 2/14/2026 MICHAEL PELHAM
CofO Issued 2/14/2026 MICHAEL PELHAM
Permit Finaled 2/14/2026 MICHAEL PELHAM

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/25/2025 COLIN LOREDO
BHO/Hillside ordinance Cleared 4/25/2025 COLIN LOREDO
BHO/Hillside ordinance Cleared 4/25/2025 COLIN LOREDO
BHO/Hillside ordinance Cleared 4/25/2025 COLIN LOREDO
BHO/Hillside ordinance Cleared 4/25/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 4/25/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 4/25/2025 COLIN LOREDO
Sewer availability Cleared 4/25/2025 COLIN LOREDO
Hydrant and Access approval Cleared 4/28/2025 KURT CORRAL
GPI Written Notices Cleared 6/6/2025 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 6/6/2025 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/18/2025 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 6/30/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 8/29/2025 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 8/29/2025 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 8/29/2025 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 8/29/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 8/29/2025 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 8/29/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 9/3/2025 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 9/23/2025 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/23/2025 Approved DAVID ANDERSON
HVAC-Rough 9/23/2025 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 9/23/2025 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 9/24/2025 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 9/26/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 9/26/2025 Approved DAVID ANDERSON
Green Building Rough 9/26/2025 Approved DAVID ANDERSON
HVAC-Rough 9/26/2025 Approved DAVID ANDERSON
PLUMBING-Rough 9/26/2025 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 9/26/2025 Approved DAVID ANDERSON
Wood Frame 9/26/2025 Approved DAVID ANDERSON
Insulation 9/30/2025 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 9/30/2025 Not Ready for Inspection DAVID ANDERSON
Insulation 10/2/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 10/2/2025 Partial Approval DAVID ANDERSON
Deputy Steel/Welding 10/3/2025 Conditional Approval DAVID MATSON
Drywall Nailing 10/6/2025 Approved DAVID ANDERSON
Deputy Drilled-In Anchors 10/23/2025 Conditional Approval DAVID MATSON
Final 12/18/2025 OK to Issue CofO DAVID ANDERSON
Green Building Final 12/18/2025 Approved DAVID ANDERSON
MERV13>=Final 12/18/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 12/18/2025 SGSOV Approved DAVID ANDERSON
Smoke Detectors 12/18/2025 Approved DAVID ANDERSON