17320 W TULSA ST 91344

Certificate Information: 17320 W TULSA ST 91344

Application / Permit
25014-20000-01270
Plan Check / Job No.
B25VN07805
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. One-story addition to (E) one-story single family dwelling.
Permit Issued
Issued on 7/3/2025
Issuing Office
Current Status
CofO Issued on 1/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2025 APPLICANT
Assigned to Plan Check Engineer 3/27/2025 ALEXANDER JOO
Corrections Issued 3/29/2025 ALEXANDER JOO
Quality Review Completed 4/14/2025 PRANITA SHAH
Plan Check Approved 6/24/2025 ALEXANDER JOO
Issued 7/3/2025 APPLICANT
CofO in Progress 12/16/2025 STEVEN BACK
Permit Finaled 1/16/2026 JOHN JANSON
CofO Issued 1/16/2026 JOHN JANSON
Permit Finaled 1/16/2026 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/28/2025 SAFA JAVANMARDI
Sewer availability Cleared 5/28/2025 SAFA JAVANMARDI
Construction within easement Cleared 6/10/2025 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 6/18/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Markarian,, Mardiros; Lic. No.: C53434 3814 VANALDEN AVE      TARZANA, CA 91356

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/15/2025 Partial Inspection STEVEN BACK
Footing/Foundation/Slab 8/6/2025 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 8/6/2025 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 8/13/2025 Not Ready for Inspection STEVEN BACK
Footing/Foundation/Slab 8/18/2025 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 8/21/2025 Not Ready for Inspection STEVEN BACK
Footing/Foundation/Slab 8/27/2025 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 10/7/2025 Approved STEVEN BACK
Footing/Foundation/Slab 10/7/2025 Approved STEVEN BACK
HVAC-Rough 10/7/2025 Approved STEVEN BACK
Deputy Wood Construction 10/8/2025 Conditional Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Approved STEVEN BACK
PLUMBING-Rough 10/9/2025 Approved STEVEN BACK
BUILDING-Rough-Frame 10/15/2025 Approved STEVEN BACK
Green Building Rough 10/15/2025 Approved STEVEN BACK
Interior/Exterior Lathing 10/15/2025 Partial Approval STEVEN BACK
Insulation 10/20/2025 Approved STEVEN BACK
Interior/Exterior Lathing 10/20/2025 Approved STEVEN BACK
Shower Pan 10/20/2025 Approved STEVEN BACK
Drywall Nailing 10/27/2025 Approved STEVEN BACK
Sewer 11/25/2025 Approved STEVEN BACK
Final 12/2/2025 Corrections Issued STEVEN BACK
Green Building Final 12/2/2025 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV Approved STEVEN BACK
Smoke Detectors 12/2/2025 Not Ready for Inspection STEVEN BACK
Final 12/8/2025 Not Ready for Inspection STEVEN BACK
Green Building Final 12/8/2025 Not Ready for Inspection STEVEN BACK
Smoke Detectors 12/8/2025 Approved STEVEN BACK
Final 12/16/2025 OK to Issue CofO STEVEN BACK
Green Building Final 12/16/2025 Approved STEVEN BACK