1208 E 49TH ST 90011
Certificate Information: 1208 E 49TH ST 90011
- Application / Permit
- 25014-20000-01262
- Plan Check / Job No.
- B25VN07796
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 1-STORY (2) BEDROOM & (1) BATHROOM (45'-2" X 20') TO (E) 1-STORY SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT) **ePlan**
- Permit Issued
- Issued on 9/8/2025
- Issuing Office
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2025 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/10/2025 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/15/2025 | JASON HEALEY |
| Applicant returned to address corrections | 7/30/2025 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 8/20/2025 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/27/2025 | NILOOFAR MEHRAIN |
| Issued | 9/8/2025 | APPLICANT |
| CofO in Progress | 4/7/2026 | ALEJANDRO DE ARTOLA |
| CofO Issued | 4/9/2026 | DEROLD HAUFF |
| Permit Finaled | 4/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/22/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 6/4/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/15/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/16/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/27/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 10/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 12/2/2025 | No Access for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/3/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 12/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 12/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 1/6/2026 | Approved | BARRY HACHE |
| Drywall Nailing | 1/13/2026 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 1/14/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 1/16/2026 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/20/2026 | Partial Approval | ALEJANDRO DE ARTOLA |
| Final | 3/10/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/10/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/10/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/10/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/16/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/16/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/16/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/16/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/24/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/6/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/6/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/6/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/7/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |