6520-6522 N ROYER AVE 91307

Certificate Information: 6520-6522 N ROYER AVE 91307

Application / Permit
25014-20000-01222
Plan Check / Job No.
B25VN07441
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Ground floor addition to enlarge kitchen and remodel portion of (E) laundry and kitchen to bedroom in (E) 1-story SFD w/attached ADU. see comments
Permit Issued
Issued on 4/8/2025
Issuing Office
Current Status
CofO Issued on 2/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2025 APPLICANT
Assigned to Plan Check Engineer 3/24/2025 DAVID CASTILLO
Corrections Issued 3/25/2025 DAVID CASTILLO
Plan Check Approved 4/3/2025 DAVID CASTILLO
Issued 4/8/2025 APPLICANT
CofO in Progress 9/26/2025 TROY SANDERS
No Progress 1/23/2026 ROBERT GOLD
CofO in Progress 1/23/2026 ROBERT GOLD
Permit Finaled 2/6/2026 JOHN JANSON
Permit Finaled 2/6/2026 JOHN JANSON
CofO Issued 2/6/2026 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/1/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 4/1/2025 COLIN LOREDO
Sewer availability Cleared 4/1/2025 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 6047 TAMPA AVE   SUITE 304    TARZANA, CA 91356

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/27/2025 Not Ready for Inspection TROY SANDERS
Pre-Inspection 5/27/2025 Partial Approval TROY SANDERS
Deputy Steel/Welding 6/5/2025 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 6/10/2025 Conditional Approval HENRY KIM
Footing/Foundation/Slab 6/10/2025 Corrections Issued JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 6/12/2025 Partial Approval GEVORK IPCHYAN
Reinforced Concrete Frame 6/12/2025 Partial Approval GEVORK IPCHYAN
Deputy Reinf. Concrete 6/16/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 6/17/2025 Approved GEVORK IPCHYAN
Footing/Foundation/Slab 6/17/2025 Approved GEVORK IPCHYAN
Reinforced Concrete Frame 6/17/2025 Approved GEVORK IPCHYAN
Deputy Reinf. Concrete 6/18/2025 Conditional Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/24/2025 Partial Approval TROY SANDERS
Wood Frame 6/24/2025 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/26/2025 Partial Approval TROY SANDERS
Insulation 6/26/2025 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 6/30/2025 Not Ready for Inspection TROY SANDERS
Deputy Steel/Welding 6/30/2025 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Not Ready for Inspection TROY SANDERS
Green Building Rough 6/30/2025 Not Ready for Inspection TROY SANDERS
Structural Steel Frame 6/30/2025 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 7/23/2025 Approved TROY SANDERS
ELECTRICAL-Rough 7/23/2025 Approved TROY SANDERS
Green Building Rough 7/23/2025 Approved TROY SANDERS
HVAC-Rough 7/23/2025 Approved TROY SANDERS
PLUMBING-Rough 7/23/2025 Approved TROY SANDERS
Service/Power Release 7/23/2025 Approved TROY SANDERS
Insulation 8/5/2025 Approved TROY SANDERS
Interior/Exterior Lathing 8/5/2025 Partial Approval TROY SANDERS
Shower Pan 8/5/2025 Approved TROY SANDERS
Drywall Nailing 8/13/2025 Approved TROY SANDERS
Interior/Exterior Lathing 8/13/2025 Partial Approval TROY SANDERS
ELECTRICAL-Final 9/25/2025 Approved TROY SANDERS
Final 9/25/2025 OK to Issue CofO TROY SANDERS
Green Building Final 9/25/2025 Approved TROY SANDERS
HVAC-Final 9/25/2025 Approved TROY SANDERS
PLUMBING-Final 9/25/2025 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Approved TROY SANDERS
Smoke Detectors 9/25/2025 Approved TROY SANDERS