15813 W COMMUNITY ST 91343

Certificate Information: 15813 W COMMUNITY ST 91343

Application / Permit
25014-20000-01201
Plan Check / Job No.
B25VN07274
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
LEGALIZE UNPERMITTED ADDITION AND CONVERSION OF CARPORT TO ACCESSORY DWELLING UNIT AND ADD TRELLIS. Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2)
Permit Issued
Issued on 5/7/2025
Issuing Office
Current Status
CofO in Progress on 4/22/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/18/2025 APPLICANT
Assigned to Plan Check Engineer 3/24/2025 JEROME MAGAT PALMA
Corrections Issued 3/25/2025 JEROME MAGAT PALMA
Building Plans Picked Up 4/1/2025 APPLICANT
Plan Check Approved 5/7/2025 ALEC MOUSAKHANIAN
Issued 5/7/2025 APPLICANT
CofO in Progress 4/22/2026 KIRK SANDERS

Permit Application Clearance Information

Address approval Cleared 4/1/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 4/1/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 4/8/2025 COLIN LOREDO
Sewer availability Cleared 4/8/2025 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/31/2025 Partial Inspection SALVADOR MARTINEZ
PLUMBING-Rough 9/4/2025 Partial Approval WAYNE REGESTER
Underground Mechanical 9/4/2025 Partial Approval WAYNE REGESTER
Footing/Foundation/Slab 9/12/2025 Not Ready for Inspection WAYNE REGESTER
Deputy Drilled-In Anchors 10/14/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/17/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/7/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 11/7/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 11/7/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 11/7/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 11/7/2025 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 11/7/2025 Approved GAREN HAYRAPETYAN
Insulation 11/17/2025 Conditional Approval GAREN HAYRAPETYAN
Interior/Exterior Lathing 11/17/2025 Approved GAREN HAYRAPETYAN
Shower Pan 11/17/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 11/24/2025 Approved WAYNE REGESTER
Insulation 11/24/2025 Approved WAYNE REGESTER
Sewer 12/12/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 12/12/2025 Partial Approval GAREN HAYRAPETYAN
Pre-Inspection 1/21/2026 Partial Inspection JENNIFER RABUCHIN
Service/Power Release 1/21/2026 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Final 3/3/2026 Corrections Issued KIRK SANDERS
Service/Power Release 3/3/2026 Not Ready for Inspection KIRK SANDERS
HVAC-Final 3/5/2026 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 4/3/2026 Approved KEVIN BERBERYAN
Final 4/3/2026 Corrections Issued KEVIN BERBERYAN
Green Building Final 4/3/2026 Approved KEVIN BERBERYAN
HVAC-Final 4/3/2026 Approved KEVIN BERBERYAN
PLUMBING-Final 4/3/2026 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 4/3/2026 SGSOV No Gas KEVIN BERBERYAN
Smoke Detectors 4/3/2026 Approved KEVIN BERBERYAN
Final 4/22/2026 OK to Issue CofO KIRK SANDERS