348 E 56TH ST 90011
Certificate Information: 348 E 56TH ST 90011
- Application / Permit
- 25014-20000-01195
- Plan Check / Job No.
- B25VN07207
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE WITH AN ADDITION TO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 5/12/2025
- Issuing Office
- Current Status
- Issued on 5/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2025 | KAMYAR EMAMI |
| Corrections Issued | 3/24/2025 | KAMYAR EMAMI |
| Applicant returned to address corrections | 4/11/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/16/2025 | LUISANGEL VALENZUELA |
| Issued | 5/12/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/1/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 4/2/2025 | SAFA JAVANMARDI |
| ZI | Cleared | 4/7/2025 | ANACANY HURTADO |
| Address approval | Cleared | 4/14/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/18/2025 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 7/18/2025 | Corrections Issued | MICHAEL LEWIS |
| Sewer | 7/18/2025 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 7/18/2025 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 8/4/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 12/8/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 12/8/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 12/8/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 12/17/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 12/17/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 12/17/2025 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 12/19/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 12/19/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 12/19/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 12/30/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 1/6/2026 | Approved | BARRY HACHE |