10522 N HELENDALE AVE 91042
Certificate Information: 10522 N HELENDALE AVE 91042
- Application / Permit
- 25014-20000-01184
- Plan Check / Job No.
- B25VN07144
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT EXISTING 2-CAR GARAGE + ADDITION TO (N) ACCESSORY DWELLING UNIT. PER GCS66323(a)(2), ALL WORK PER WFPP
- Permit Issued
- Issued on 5/5/2025
- Issuing Office
- Current Status
- Issued on 5/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 3/22/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 4/30/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/1/2025 | LUISANGEL VALENZUELA |
| Issued | 5/5/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/25/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 4/25/2025 | MICHAEL BROWN |
| Construction near power lines | Cleared | 4/28/2025 | ENRIQUE ACOSTA |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 4/28/2025 | MICHAEL BROWN |
| Grading Pre-Inspection | Cleared | 4/30/2025 | LUISANGEL VALENZUELA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/2/2025 | Partial Approval | WAYNE REGESTER |
| Footing/Foundation/Slab | 9/24/2025 | Not Ready for Inspection | WILLIAM WREN |
| Deputy Drilled-In Anchors | 10/6/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 10/7/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 12/2/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 12/2/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 12/2/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 12/16/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Insulation | 12/16/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Shower Pan | 12/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 12/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 12/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 12/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 12/26/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 12/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 1/14/2026 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 1/14/2026 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 1/26/2026 | Approved | NICHOLAS TROWBRIDGE |