10620 N AMESTOY AVE 91344

Certificate Information: 10620 N AMESTOY AVE 91344

Application / Permit
25014-20000-01172
Plan Check / Job No.
B25VN07118
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: NEW REAR ADDITION TO THE (E) SINGLE FAMILY DWELLING AND NEW PATIO COVER ADDITION. INTERIOR REMODEL TO THE (E) SINGLE FAMILY DWELLING. CREATE NEW BEDROOM, RELOCATE KITCHEN, EXTEND LIVING ROOM.
Permit Issued
Issued on 5/15/2025
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2025 APPLICANT
Assigned to Plan Check Engineer 3/19/2025 GIOVANNY CHAVEZ
Corrections Issued 3/20/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 5/6/2025 GIOVANNY CHAVEZ
Plan Check Approved 5/9/2025 ALEC MOUSAKHANIAN
Issued 5/15/2025 APPLICANT
CofO in Progress 4/29/2026 KEVIN BERBERYAN
CofO Issued 6/4/2026 RUBEN SALAS
Permit Finaled 6/4/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/22/2025 LEE GUILBEAUX
Sewer availability Cleared 3/22/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/22/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/24/2025 LEE GUILBEAUX
Construction near power lines Cleared 5/2/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mezey,, Steven William; Lic. No.: NA2665       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/10/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/14/2025 Partial Approval CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 7/21/2025 Conditional Approval RAUL OLAGI
Service/Power Release 7/24/2025 Approved CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 7/31/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/31/2025 Approved CHRISTOPHER ROJAS
Deputy Reinf. Concrete 8/4/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/6/2025 Partial Approval NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 8/6/2025 Partial Approval NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Partial Approval NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 8/22/2025 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Partial Approval JACK KARGODORIAN
Green Building Rough 8/22/2025 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Partial Inspection CHRISTOPHER ROJAS
Pre-Inspection 9/17/2025 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/23/2025 Partial Approval CHRISTOPHER ROJAS
Insulation 9/23/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/15/2025 Conditional Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/15/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 10/15/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 10/15/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 10/15/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/20/2025 Partial Approval LOUIS ESCOTO
BUILDING-Rough-Frame 10/29/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 10/29/2025 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 10/29/2025 Corrections Issued CHRISTOPHER ROJAS
Insulation 10/29/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/4/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 11/4/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 11/4/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 11/17/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 12/17/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 3/12/2026 Corrections Issued CHRISTOPHER ROJAS
Final 3/12/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 3/12/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 3/12/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 3/12/2026 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/12/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 3/12/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 3/20/2026 Approved KEVIN BERBERYAN
Final 3/20/2026 Partial Approval KEVIN BERBERYAN
HVAC-Final 3/20/2026 Approved KEVIN BERBERYAN
PLUMBING-Final 3/20/2026 Approved KEVIN BERBERYAN
Final 4/29/2026 OK to Issue CofO KEVIN BERBERYAN