10620 N AMESTOY AVE 91344
Certificate Information: 10620 N AMESTOY AVE 91344
- Application / Permit
- 25014-20000-01172
- Plan Check / Job No.
- B25VN07118
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: NEW REAR ADDITION TO THE (E) SINGLE FAMILY DWELLING AND NEW PATIO COVER ADDITION. INTERIOR REMODEL TO THE (E) SINGLE FAMILY DWELLING. CREATE NEW BEDROOM, RELOCATE KITCHEN, EXTEND LIVING ROOM.
- Permit Issued
- Issued on 5/15/2025
- Issuing Office
- Current Status
- CofO Issued on 6/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 3/20/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 5/6/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 5/9/2025 | ALEC MOUSAKHANIAN |
| Issued | 5/15/2025 | APPLICANT |
| CofO in Progress | 4/29/2026 | KEVIN BERBERYAN |
| CofO Issued | 6/4/2026 | RUBEN SALAS |
| Permit Finaled | 6/4/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/22/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/22/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/22/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2025 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 5/2/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mezey,, Steven William; Lic. No.: NA2665 | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/10/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 7/14/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 7/21/2025 | Conditional Approval | RAUL OLAGI |
| Service/Power Release | 7/24/2025 | Approved | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 7/31/2025 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 7/31/2025 | Approved | CHRISTOPHER ROJAS |
| Deputy Reinf. Concrete | 8/4/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/6/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 8/22/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 8/22/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 9/17/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 9/23/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/15/2025 | Conditional Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/15/2025 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 10/15/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/15/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/15/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/20/2025 | Partial Approval | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 10/29/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 10/29/2025 | Partial Approval | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/29/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Insulation | 10/29/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/4/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 11/4/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/4/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 11/17/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 12/17/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 3/12/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 3/12/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 3/12/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 3/12/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 3/12/2026 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/12/2026 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/12/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 3/20/2026 | Approved | KEVIN BERBERYAN |
| Final | 3/20/2026 | Partial Approval | KEVIN BERBERYAN |
| HVAC-Final | 3/20/2026 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 3/20/2026 | Approved | KEVIN BERBERYAN |
| Final | 4/29/2026 | OK to Issue CofO | KEVIN BERBERYAN |