9452-9454 N NAGLE AVE 91331

Certificate Information: 9452-9454 N NAGLE AVE 91331

Application / Permit
25014-20000-01166
Plan Check / Job No.
B25VN07106
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(E) attached Garage conversion into a partial storage and partial Accessory Dwelling Unit with a 2-story Addition on (E) SFD to become a two story SFD w/ attached two story ADU per gc & 66323(a)(1)
Permit Issued
Issued on 7/16/2025
Issuing Office
Current Status
Issued on 7/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/17/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 SERGIO GUTIERREZ
Corrections Issued 3/26/2025 SERGIO GUTIERREZ
Quality Review Completed 3/26/2025 PRANITA SHAH
Plan Check Approved 6/27/2025 SERGIO GUTIERREZ
Issued 7/16/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/28/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 3/28/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 4/7/2025 JEANIE LAM
Sewer availability Cleared 4/7/2025 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/3/2025 Partial Approval VINCENT HANLEY
Sewer 9/3/2025 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 9/8/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 9/11/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/22/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Partial Approval VINCENT HANLEY
Deputy Wood Construction 1/21/2026 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 1/28/2026 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/28/2026 Approved VINCENT HANLEY
Green Building Rough 1/28/2026 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 1/28/2026 Approved VINCENT HANLEY
Insulation 3/11/2026 Approved OGANES TARAKHCHYAN