16738 W GILMORE ST 91406
Certificate Information: 16738 W GILMORE ST 91406
- Application / Permit
- 25014-20000-01162
- Plan Check / Job No.
- B25VN07079
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: NEW ACCESSORY DWELLING UNIT ADDITION TO THE (E) DETACHED GARAGE PER LAMC 12.22 A.33(b)(1),(c),(d),(h) AND (k).
- Permit Issued
- Issued on 5/2/2025
- Issuing Office
- Current Status
- CofO Issued on 12/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 3/20/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 4/30/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 5/1/2025 | NAREG ATARIAN |
| Issued | 5/2/2025 | APPLICANT |
| CofO in Progress | 12/17/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 12/19/2025 | RUBEN SALAS |
| CofO Issued | 12/19/2025 | RUBEN SALAS |
| Permit Finaled | 12/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/21/2025 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 3/21/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 3/21/2025 | EDGAR ALCARAZ |
| ZI | Cleared | 3/22/2025 | BRENNEN OBETO |
| Construction near power lines | Cleared | 4/28/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Seven Seas Construction Services Inc; Lic. No.: 1065345-B | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/23/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 5/27/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 5/28/2025 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 5/29/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Excavation/Setback/Form/Re-Bar | 6/3/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 7/14/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/14/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/16/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/16/2025 | Corrections Issued | JAVIER RAMOS JR |
| Underground Mechanical | 7/16/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 8/8/2025 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/8/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 8/8/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 8/8/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/8/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/12/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 8/12/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 8/12/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 8/20/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 8/20/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Insulation | 8/22/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/22/2025 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 8/22/2025 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 9/2/2025 | Corrections Issued | LOUIS ESCOTO |
| Drywall Nailing | 10/27/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 10/27/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 10/29/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 10/29/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 10/29/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 10/29/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 10/29/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 10/29/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 12/17/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |