12044 W NATIONAL BLVD 90064

Certificate Information: 12044 W NATIONAL BLVD 90064

Application / Permit
25014-20000-01114
Plan Check / Job No.
B25VN06751
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE ADDITION (20' x 5') TO (E) DETACHED GARAGE & ADD (N) 2ND STORY ADU ON TOP [PER PER LAMC 12.22 A.33(b)(1)].
Permit Issued
Issued on 5/7/2025
Issuing Office
Current Status
CofO Issued on 11/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 EDWARD MEHRABIAN
Corrections Issued 3/22/2025 EDWARD MEHRABIAN
Quality Review Completed 3/24/2025 OMID HEDAYAT
Building Plans Picked Up 3/25/2025 APPLICANT
Applicant returned to address corrections 4/9/2025 EDWARD MEHRABIAN
Plan Check Approved 5/7/2025 EDWARD MEHRABIAN
Issued 5/7/2025 APPLICANT
CofO in Progress 11/14/2025 KIRK SANDERS
Permit Finaled 11/20/2025 RICHARD STEINBACH
CofO Issued 11/20/2025 RICHARD STEINBACH
Permit Finaled 11/20/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/21/2025 CELINA MORENO
Roof/Waste drainage to street Cleared 3/21/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/27/2025 DAVID LOPEZ
Sewer availability Cleared 3/27/2025 DAVID LOPEZ
Specific Plan Cleared 4/1/2025 HAMID GHAEMMAGHAMI
Grading Pre-Inspection Cleared 4/18/2025 CHARLES POWELL
GPI Written Notices Cleared 5/7/2025 EDWARD MEHRABIAN

Contact Information

Contractor Neo Builders And Design Inc; Lic. No.: 1114778-B 12005 ALBERS APT 233      NORTH HOLLYWOOD, CA 91607
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/29/2025 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 5/29/2025 Approved KIRK SANDERS
Underground Mechanical 5/29/2025 Approved KIRK SANDERS
Deputy Drilled-In Anchors 5/30/2025 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 6/26/2025 Corrections Issued WILBER ROSALES
ELECTRICAL-Rough 7/8/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/8/2025 Approved WILBER ROSALES
HVAC-Rough 7/8/2025 Approved WILBER ROSALES
PLUMBING-Rough 7/8/2025 Approved WILBER ROSALES
Insulation 7/14/2025 Not Ready for Inspection WILBER ROSALES
Insulation 7/18/2025 No Access for Inspection WILBER ROSALES
Insulation 7/21/2025 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 7/24/2025 Approved BOBBY KEY
Drywall Nailing 7/24/2025 Corrections Issued BOBBY KEY
Green Building Rough 7/24/2025 Approved BOBBY KEY
Insulation 7/24/2025 Approved BOBBY KEY
Interior/Exterior Lathing 7/24/2025 Partial Approval BOBBY KEY
Drywall Nailing 8/1/2025 Approved KIRK SANDERS
Shower Pan 8/1/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 8/6/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 10/31/2025 Approved EVAN COOPER
Final 10/31/2025 Corrections Issued EVAN COOPER
Green Building Final 10/31/2025 Approved EVAN COOPER
HVAC-Final 10/31/2025 Corrections Issued EVAN COOPER
PLUMBING-Final 10/31/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 10/31/2025 Approved EVAN COOPER
ELECTRICAL-Final 11/7/2025 Approved KIRK SANDERS
Final 11/7/2025 Corrections Issued KIRK SANDERS
HVAC-Final 11/7/2025 Not Ready for Inspection KIRK SANDERS
PLUMBING-Final 11/7/2025 Approved KIRK SANDERS
Final 11/14/2025 OK to Issue CofO KIRK SANDERS