12995 N EL DORADO AVE 91342
Certificate Information: 12995 N EL DORADO AVE 91342
- Application / Permit
- 25014-20000-01077
- Plan Check / Job No.
- B25VN06531
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 13' X 15' ADDITION TO THE (E) SFD, WITH AN INTERIOR REMODEL TO RELOCATE THE (E) KITCHEN.
- Permit Issued
- Issued on 3/14/2025
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 4/24/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2025 | ALEC MOUSAKHANIAN |
| Corrections Issued | 3/11/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 3/14/2025 | HAYATO TSUCHIYA |
| Issued | 3/14/2025 | APPLICANT |
| CofO in Progress | 4/24/2026 | KEVIN BERBERYAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/12/2025 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 3/14/2025 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Corrections Issued | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 5/6/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/12/2025 | Approved | LOUIS ESCOTO |
| Insulation | 5/19/2025 | Corrections Issued | LOUIS ESCOTO |
| Drywall Nailing | 5/21/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/21/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/5/2025 | Approved | KEVIN BERBERYAN |
| Final | 9/5/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 9/5/2025 | Approved | KEVIN BERBERYAN |
| Green Building Final | 9/5/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 9/5/2025 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/5/2025 | Approved | KEVIN BERBERYAN |
| Final | 4/24/2026 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 4/24/2026 | Approved | KEVIN BERBERYAN |