12995 N EL DORADO AVE 91342

Certificate Information: 12995 N EL DORADO AVE 91342

Application / Permit
25014-20000-01077
Plan Check / Job No.
B25VN06531
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 13' X 15' ADDITION TO THE (E) SFD, WITH AN INTERIOR REMODEL TO RELOCATE THE (E) KITCHEN.
Permit Issued
Issued on 3/14/2025
Issuing Office
Metro
Current Status
CofO in Progress on 4/24/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/11/2025 APPLICANT
Assigned to Plan Check Engineer 3/11/2025 ALEC MOUSAKHANIAN
Corrections Issued 3/11/2025 ALEC MOUSAKHANIAN
Plan Check Approved 3/14/2025 HAYATO TSUCHIYA
Issued 3/14/2025 APPLICANT
CofO in Progress 4/24/2026 KEVIN BERBERYAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/12/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/12/2025 CARLOS AGUILERA
Grading Pre-Inspection Cleared 3/14/2025 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/4/2025 Corrections Issued KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 5/6/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 5/12/2025 Approved LOUIS ESCOTO
Insulation 5/19/2025 Corrections Issued LOUIS ESCOTO
Drywall Nailing 5/21/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 5/21/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/2/2025 SGSOV Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 9/5/2025 Approved KEVIN BERBERYAN
Final 9/5/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 9/5/2025 Approved KEVIN BERBERYAN
Green Building Final 9/5/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 9/5/2025 Approved KEVIN BERBERYAN
Smoke Detectors 9/5/2025 Approved KEVIN BERBERYAN
Final 4/24/2026 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 4/24/2026 Approved KEVIN BERBERYAN