5873 N ALONZO AVE 91316

Certificate Information: 5873 N ALONZO AVE 91316

Application / Permit
25014-20000-01074
Plan Check / Job No.
B25VN06500
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL INT & EXT WALLS OF (E) ONE STORY SINGLE FAMILY DWELLING EXCEPT FOR PORTION OF THE FRONT WALL AND ERECT AN IRR. SHAPED 49'-11" x 53'-5" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE & OPEN TRELLIS; NFPA-13D THRU-OUT
Permit Issued
Issued on 4/8/2025
Issuing Office
Valley
Current Status
Issued on 4/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/11/2025 APPLICANT
Assigned to Plan Check Engineer 3/13/2025 SEAN SHAHMIRI
Corrections Issued 3/17/2025 SEAN SHAHMIRI
Quality Review Completed 3/17/2025 STEVEN KIM
Building Plans Picked Up 3/17/2025 APPLICANT
Applicant returned to address corrections 4/1/2025 SEAN SHAHMIRI
Plan Check Approved 4/8/2025 ALFRED RAMIREZ
Issued 4/8/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/17/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/17/2025 LEE GUILBEAUX
Sewer availability Cleared 3/17/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/17/2025 LEE GUILBEAUX
ZI Cleared 4/1/2025 GEORGIA SMITH

Contact Information

Contractor Owner-Builder       ,
Engineer Mosesian,, Peter; Lic. No.: C95745 86 SMOKE TREE AVE      OAK PARK, CA 91377

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/28/2025 Conditional Approval JON MCHUGH
Footing/Foundation/Slab 5/1/2025 Corrections Issued MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 5/2/2025 Corrections Issued MORRIS JACKSON
Footing/Foundation/Slab 5/2/2025 Partial Approval MORRIS JACKSON
Special/Order Compliance 5/2/2025 Corrections Issued MORRIS JACKSON
PLUMBING-Rough 5/8/2025 Partial Approval MORRIS JACKSON
Deputy Drilled-In Anchors 5/16/2025 Conditional Approval MORRIS JACKSON
Deputy Reinf. Concrete 5/16/2025 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 5/16/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 6/3/2025 Partial Approval MORRIS JACKSON
Green Building Rough 6/3/2025 Not Ready for Inspection MORRIS JACKSON
Verify Sprinkler Sign Off 6/3/2025 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 9/22/2025 Corrections Issued MORRIS JACKSON
ELECTRICAL-Rough 9/22/2025 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 Partial Approval MORRIS JACKSON
Gas Test 9/22/2025 Approved MORRIS JACKSON
HVAC-Rough 9/22/2025 Approved MORRIS JACKSON
PLUMBING-Rough 9/22/2025 Approved MORRIS JACKSON
ELECTRICAL-Rough 9/23/2025 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 10/6/2025 Corrections Issued MORRIS JACKSON
Interior/Exterior Lathing 10/6/2025 Partial Approval MORRIS JACKSON
Sewer 10/6/2025 Approved MORRIS JACKSON
BUILDING-Rough-Frame 10/22/2025 Approved MORRIS JACKSON
Green Building Rough 10/22/2025 Approved MORRIS JACKSON
Insulation 10/22/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/22/2025 Partial Approval MORRIS JACKSON
Drywall Nailing 11/4/2025 Approved MORRIS JACKSON
Shower Pan 11/4/2025 Approved MORRIS JACKSON
Verify Sprinkler Sign Off 11/4/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/18/2025 Approved JON MCHUGH