7723 W JAYSEEL ST 91042

Certificate Information: 7723 W JAYSEEL ST 91042

Application / Permit
25014-20000-01016
Plan Check / Job No.
B25VN06104
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION AND INTERIOR REMODEL TO (E) SFD
Permit Issued
Issued on 5/8/2025
Issuing Office
Current Status
CofO Issued on 1/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2025 APPLICANT
Assigned to Plan Check Engineer 3/17/2025 ISIS ARGUETA
Corrections Issued 3/18/2025 ISIS ARGUETA
Applicant returned to address corrections 4/15/2025 NAREG ATARIAN
Plan Check Approved 5/7/2025 ISIS ARGUETA
Issued 5/8/2025 APPLICANT
CofO in Progress 12/11/2025 NICHOLAS TROWBRIDGE
Permit Finaled 1/13/2026 RUBEN SALAS
CofO Issued 1/13/2026 RUBEN SALAS
Permit Finaled 1/13/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/1/2025 COLIN LOREDO
Sewer availability Cleared 4/1/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 4/2/2025 COLIN LOREDO
Grading Pre-Inspection Cleared 4/9/2025 ROBERT PINA

Contact Information

Contractor Owner-Builder       ,
Engineer Danialian,, Derik; Lic. No.: C94256 15904 INDEX ST.      GRANADA HILLS, CA 91344

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/14/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 7/16/2025 Approved MATTHEW NELSON
Footing/Foundation/Slab 7/16/2025 Approved MATTHEW NELSON
Underground Mechanical 7/16/2025 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 7/25/2025 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/14/2025 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/18/2025 Approved WILLIAM WREN
PLUMBING-Rough 8/19/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/27/2025 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 8/27/2025 Approved WILLIAM WREN
HVAC-Rough 8/27/2025 Approved WILLIAM WREN
Shower Pan 8/27/2025 Not Ready for Inspection WILLIAM WREN
Interior/Exterior Lathing 9/2/2025 Approved WAYNE REGESTER
Shower Pan 9/2/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 9/12/2025 Approved KEVIN BERBERYAN
Insulation 9/16/2025 Approved JOAQUIN GREENOUGH
Drywall Nailing 9/23/2025 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 11/25/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Final 12/10/2025 OK to Issue CofO NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 12/10/2025 SGSOV Approved NICHOLAS TROWBRIDGE
Smoke Detectors 12/10/2025 Approved NICHOLAS TROWBRIDGE