7029 N RHEA AVE 91335
Certificate Information: 7029 N RHEA AVE 91335
- Application / Permit
- 25014-20000-01011
- Plan Check / Job No.
- B25VN06032
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED STORAGE AND (N) ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(b)(1). (E) ATTACHED PATIO COVER TO REMAIN. WORK DONE PER WFPP.
- Permit Issued
- Issued on 4/23/2025
- Issuing Office
- Valley
- Current Status
- Issued on 4/23/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2025 | MADISON ODELL |
| Corrections Issued | 3/11/2025 | MADISON ODELL |
| Building Plans Picked Up | 3/19/2025 | APPLICANT |
| Issued | 4/23/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/11/2025 | MICHAEL BROWN |
| ZI | Cleared | 4/11/2025 | JASON CHAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 4/14/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 4/14/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/7/2025 | Conditional Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 5/9/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Green Building Rough | 5/9/2025 | Not Ready for Inspection | JUAN ALVARADO |
| PLUMBING-Rough | 5/16/2025 | Approved | JUAN ALVARADO |
| Footing/Foundation/Slab | 5/22/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 6/24/2025 | Partial Approval | JUAN ALVARADO |
| Green Building Rough | 6/24/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Interior/Exterior Lathing | 7/23/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 7/23/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Rough | 8/19/2025 | Partial Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 8/28/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 8/28/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 9/4/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 9/4/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 9/4/2025 | Approved | JUAN ALVARADO |
| Insulation | 9/12/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 9/12/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 9/12/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 9/23/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 9/23/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Rough | 4/23/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |