607-607 1/2 W 101ST ST 90044

Certificate Information: 607-607 1/2 W 101ST ST 90044

Application / Permit
25014-20000-00973
Plan Check / Job No.
B25VN05791
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE PORTION OF (E) SFD, 29'-0" X 17'-0" ACCESSORY DWELLING UNIT ADDITION TO (E) SFD PER GCS 66323(a)(1). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 4/2/2025
Issuing Office
Valley
Current Status
Issued on 4/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/4/2025 APPLICANT
Assigned to Plan Check Engineer 3/7/2025 ARTIN ZARUKIAN
Corrections Issued 3/7/2025 ARTIN ZARUKIAN
Building Plans Picked Up 3/13/2025 APPLICANT
Plan Check Approved 3/28/2025 GIOVANNY CHAVEZ
Issued 4/2/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/19/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/19/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/21/2025 BIAINA HARITUNIAN
Sewer availability Cleared 3/21/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/11/2025 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 4/14/2025 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 4/29/2025 Approved BEN MOLSTAD
BUILDING-Rough-Frame 5/6/2025 Not Ready for Inspection BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Corrections Issued BEN MOLSTAD
Green Building Rough 5/6/2025 Not Ready for Inspection BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 5/7/2025 Partial Approval BEN MOLSTAD
BUILDING-Rough-Frame 5/12/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 5/12/2025 Corrections Issued BEN MOLSTAD
Gas Test 5/12/2025 Approved BEN MOLSTAD
Green Building Rough 5/12/2025 Approved BEN MOLSTAD
HVAC-Rough 5/12/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 5/12/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 5/12/2025 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 5/12/2025 SGSOV Not Ready BEN MOLSTAD
Shower Pan 5/12/2025 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 5/14/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 5/14/2025 Corrections Issued BEN MOLSTAD
Insulation 5/14/2025 Not Ready for Inspection BEN MOLSTAD
Interior/Exterior Lathing 5/14/2025 Approved BEN MOLSTAD
PLUMBING-Rough 5/14/2025 Approved BEN MOLSTAD
Shower Pan 5/14/2025 Approved BEN MOLSTAD
Insulation 5/15/2025 Partial Approval BEN MOLSTAD
ELECTRICAL-Rough 5/16/2025 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 5/16/2025 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Approved BEN MOLSTAD
Insulation 5/20/2025 Partial Approval BEN MOLSTAD
Drywall Nailing 5/23/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 5/23/2025 Approved BEN MOLSTAD
BUILDING-Rough-Frame 6/24/2025 Approved BEN MOLSTAD
ELECTRICAL-Final 6/24/2025 Not Ready for Inspection BEN MOLSTAD
Final 6/24/2025 Corrections Issued BEN MOLSTAD
Green Building Final 6/24/2025 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 6/24/2025 Corrections Issued BEN MOLSTAD
PLUMBING-Final 6/24/2025 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 6/24/2025 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 6/24/2025 Approved BEN MOLSTAD
ELECTRICAL-Final 6/27/2025 Corrections Issued BEN MOLSTAD
Final 6/27/2025 Corrections Issued BEN MOLSTAD
Green Building Final 6/27/2025 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Not Required BEN MOLSTAD
Service/Power Release 6/27/2025 Not Ready for Inspection BEN MOLSTAD
Final 8/22/2025 Corrections Issued JOSEPH MCGARRY
Green Building Final 8/22/2025 Not Ready for Inspection JOSEPH MCGARRY
Service/Power Release 8/22/2025 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Final 3/20/2026 Approved ARTHUR NEGRETE
Final 3/20/2026 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 3/20/2026 Approved ARTHUR NEGRETE
HVAC-Final 3/20/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 3/20/2026 Approved ARTHUR NEGRETE
Service/Power Release 3/20/2026 Approved ARTHUR NEGRETE
Final 3/31/2026 No Access for Inspection BEN MOLSTAD
Final 4/2/2026 Corrections Issued BEN MOLSTAD
Final 4/10/2026 Corrections Issued BEN MOLSTAD