4514 N ELLENWOOD DR 90041
Certificate Information: 4514 N ELLENWOOD DR 90041
- Application / Permit
- 25014-20000-00962
- Plan Check / Job No.
- B25VN05713
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT AND ADDITION PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
- Permit Issued
- Issued on 4/15/2025
- Issuing Office
- Current Status
- CofO Issued on 10/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2025 | JESSE ARELLANO |
| Corrections Issued | 3/8/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 3/11/2025 | APPLICANT |
| Plan Check Approved | 4/15/2025 | YAQUB MIRZA |
| Issued | 4/15/2025 | APPLICANT |
| CofO in Progress | 10/17/2025 | DAVID WILLIAMS |
| Permit Finaled | 10/19/2025 | DEROLD HAUFF |
| CofO Issued | 10/19/2025 | DEROLD HAUFF |
| Permit Finaled | 10/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2025 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2025 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 3/10/2025 | CHRISTINA BRACO |
| Sewer availability | Cleared | 3/10/2025 | CHRISTINA BRACO |
| GPI Written Notices | Cleared | 4/15/2025 | JESSE ARELLANO |
| Grading Pre-Inspection | Cleared | 4/15/2025 | JONATHAN HOM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/29/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| PLUMBING-Rough | 6/27/2025 | Approved | DAVID WILLIAMS |
| Footing/Foundation/Slab | 7/7/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2025 | Partial Approval | DAVID WILLIAMS |
| Green Building Rough | 7/31/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Rough | 8/15/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/15/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/19/2025 | Approved | DAVID WILLIAMS |
| Insulation | 8/21/2025 | Approved | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 8/22/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 8/22/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 8/22/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 8/28/2025 | Approved | DAVID WILLIAMS |
| Final | 10/10/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 10/10/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 10/10/2025 | Approved | NICHOLAS LOPEZ |
| Final | 10/16/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Final | 10/16/2025 | Approved | DAVID WILLIAMS |
| Final | 10/17/2025 | OK to Issue CofO | DAVID WILLIAMS |