7324-7326 N LINDLEY AVE 91335

Certificate Information: 7324-7326 N LINDLEY AVE 91335

Application / Permit
25014-20000-00953
Plan Check / Job No.
B25VN05621
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE PORTION OF EXISTING PATIO COVER. NEW ADDITION FOR JUNIOR ACCESSORY DWELLING UNIT PER 66323(a)(1) and 66333. WORK DONE PER WFPP.
Permit Issued
Issued on 3/24/2025
Issuing Office
Valley
Current Status
CofO Issued on 12/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2025 APPLICANT
Assigned to Plan Check Engineer 3/7/2025 JESSE ARELLANO
Corrections Issued 3/8/2025 JESSE ARELLANO
Building Plans Picked Up 3/14/2025 APPLICANT
Issued 3/24/2025 APPLICANT
CofO in Progress 11/17/2025 JUAN ALVARADO
Permit Finaled 12/4/2025 JOHN JANSON
CofO Issued 12/4/2025 JOHN JANSON
Permit Finaled 12/4/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/18/2025 KEVIN CHUNG
Roof/Waste drainage to street Cleared 3/18/2025 KEVIN CHUNG
Eng Process Fee Ord 176,300 Cleared 3/19/2025 KEVIN CHUNG
Sewer availability Cleared 3/19/2025 KEVIN CHUNG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/21/2025 Conditional Approval ROBERT GOLD
Deputy Other (see comments) 4/21/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 5/1/2025 Corrections Issued JUAN ALVARADO
Underground Mechanical 5/1/2025 Corrections Issued JUAN ALVARADO
Deputy Drilled-In Anchors 5/14/2025 Approved JUAN ALVARADO
Deputy Other (see comments) 5/14/2025 Approved JUAN ALVARADO
Footing/Foundation/Slab 5/14/2025 Corrections Issued JUAN ALVARADO
Gas Test 5/14/2025 Approved JUAN ALVARADO
Underground Mechanical 5/14/2025 Approved JUAN ALVARADO
Footing/Foundation/Slab 6/11/2025 Approved JUAN ALVARADO
Wood Frame 7/16/2025 Not Ready for Inspection JUAN ALVARADO
ELECTRICAL-Rough 8/1/2025 Approved JUAN ALVARADO
Wood Frame 8/1/2025 Approved JUAN ALVARADO
HVAC-Rough 8/20/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 8/20/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 8/28/2025 Approved JUAN ALVARADO
Green Building Rough 8/28/2025 Approved JUAN ALVARADO
PLUMBING-Rough 8/28/2025 Approved JUAN ALVARADO
Wood Frame 8/28/2025 Approved JUAN ALVARADO
Insulation 9/5/2025 Approved JUAN ALVARADO
Shower Pan 9/5/2025 Approved JUAN ALVARADO
Drywall Nailing 9/17/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 9/17/2025 Approved JUAN ALVARADO
Final 10/22/2025 Corrections Issued JUAN ALVARADO
Green Building Final 10/22/2025 Approved JUAN ALVARADO
PLUMBING-Final 10/22/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 10/22/2025 SGSOV Approved JUAN ALVARADO
Smoke Detectors 10/22/2025 Approved JUAN ALVARADO
Final 11/6/2025 Corrections Issued JUAN ALVARADO
ELECTRICAL-Final 11/17/2025 Approved JUAN ALVARADO
Final 11/17/2025 OK to Issue CofO JUAN ALVARADO
HVAC-Final 11/17/2025 Approved JUAN ALVARADO