6540-6544 N VALLEY CIRCLE BLVD 91307

Certificate Information: 6540-6544 N VALLEY CIRCLE BLVD 91307

Application / Permit
25014-20000-00947
Plan Check / Job No.
B25VN05548
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN CONVERT 20' X 20' ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GC66323(a)(1) and 66333 AND ADD 20' X 20' AT 2ND FLOOR FOR ACCESSORY DWELLING UNIT PER LAMC12.22A.33(c) and(e). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/14/2025
Issuing Office
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 RAPHAEL ROSAS
Corrections Issued 3/27/2025 RAPHAEL ROSAS
Quality Review Completed 4/2/2025 STEVEN KIM
Applicant returned to address corrections 4/16/2025 RAPHAEL ROSAS
Applicant returned to address corrections 5/6/2025 RAPHAEL ROSAS
Applicant returned to address corrections 5/14/2025 RAPHAEL ROSAS
Applicant returned to address corrections 6/27/2025 RAPHAEL ROSAS
Applicant returned to address corrections 7/17/2025 RAPHAEL ROSAS
Plan Check Approved 7/30/2025 RAPHAEL ROSAS
Issued 8/14/2025 APPLICANT
CofO in Progress 11/21/2025 GEVORK IPCHYAN
Permit Finaled 12/12/2025 JOHN JANSON
CofO Issued 12/12/2025 JOHN JANSON
Permit Finaled 12/12/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/5/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 4/5/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 4/7/2025 COLIN LOREDO
Sewer availability Cleared 4/7/2025 COLIN LOREDO

Contact Information

Contractor S & T Builders; Lic. No.: 1090121-B       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/28/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 8/29/2025 Approved GEVORK IPCHYAN
Sewer 8/29/2025 Approved GEVORK IPCHYAN
Wood Frame 9/4/2025 Not Ready for Inspection GEVORK IPCHYAN
Wood Frame 9/8/2025 Approved GEVORK IPCHYAN
Deputy Wood Construction 9/11/2025 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Partial Approval GEVORK IPCHYAN
Green Building Rough 9/23/2025 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 9/25/2025 Corrections Issued SCOTT SOBEL
ELECTRICAL-Rough 9/25/2025 Approved SCOTT SOBEL
HVAC-Rough 9/25/2025 Approved SCOTT SOBEL
PLUMBING-Rough 9/25/2025 Corrections Issued SCOTT SOBEL
BUILDING-Rough-Frame 9/29/2025 Partial Approval GEVORK IPCHYAN
Green Building Rough 9/29/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 9/29/2025 Approved GEVORK IPCHYAN
Insulation 10/2/2025 Approved ARUTYUN MADATYAN
Shower Pan 10/2/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 10/6/2025 Approved GEVORK IPCHYAN
Insulation 10/6/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 10/6/2025 Partial Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 11/18/2025 Approved GEVORK IPCHYAN
Final 11/18/2025 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 11/18/2025 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 11/18/2025 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 11/18/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Final 11/21/2025 Approved GEVORK IPCHYAN
Final 11/21/2025 OK to Issue CofO GEVORK IPCHYAN
HVAC-Final 11/21/2025 Approved GEVORK IPCHYAN