7740 N OAK PARK AVE 91406
Certificate Information: 7740 N OAK PARK AVE 91406
- Application / Permit
- 25014-20000-00928
- Plan Check / Job No.
- B25VN05474
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert (E) detached garage and addition to build an 826 ADU. Per LAMC 12.22 A.33 (c)-(d)Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2).
- Permit Issued
- Issued on 10/17/2025
- Issuing Office
- Current Status
- CofO Issued on 7/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2025 | ALFREDO JARA |
| Corrections Issued | 3/6/2025 | ALFREDO JARA |
| Applicant returned to address corrections | 6/6/2025 | ALFREDO JARA |
| Plan Check Approved | 8/5/2025 | ALFREDO JARA |
| Issued | 10/17/2025 | APPLICANT |
| CofO in Progress | 6/3/2026 | JAVIER RAMOS JR |
| CofO Issued | 7/1/2026 | RUBEN SALAS |
| Permit Finaled | 7/1/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/16/2025 | GEVORK KARAPETYAN |
| Address approval | Cleared | 4/28/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 4/28/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 7/30/2025 | DERRICK MAGEE |
Contact Information
| Contractor | J & A Legacy Building Inc; Lic. No.: 1064831-B | , |
| Engineer | Castillo,, Margarito; Lic. No.: NA4808 | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/7/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 11/18/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 12/12/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Deputy Wood Construction | 12/12/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2025 | Partial Approval | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 12/22/2025 | Partial Approval | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 12/22/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| HVAC-Rough | 12/22/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 12/22/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2025 | Approved | LOUIS ESCOTO |
| Insulation | 12/29/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 12/29/2025 | Partial Approval | LOUIS ESCOTO |
| Shower Pan | 12/29/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 12/31/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 1/8/2026 | Approved | CHRISTOPHER MORFIN |
| Underground Mechanical | 1/21/2026 | Corrections Issued | RYAN SALAZAR |
| Underground Mechanical | 1/26/2026 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 4/21/2026 | Approved | KIRK SANDERS |
| Final | 4/21/2026 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Not Required | KIRK SANDERS |
| Service/Power Release | 4/21/2026 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 4/21/2026 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 4/30/2026 | Approved | JAVIER RAMOS JR |
| Final | 4/30/2026 | Partial Approval | JAVIER RAMOS JR |
| Green Building Final | 4/30/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 4/30/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/30/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/30/2026 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 4/30/2026 | Approved | JAVIER RAMOS JR |
| Final | 6/3/2026 | OK to Issue CofO | JAVIER RAMOS JR |