20355-20357 W CLARK ST 91367

Certificate Information: 20355-20357 W CLARK ST 91367

Application / Permit
25014-20000-00921
Plan Check / Job No.
B25VN05450
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) 1128 SF SFD EXCEPT FOR 17'-3" AND 12'-1" OF WALLS AND FOUNDATION. REBUILD 55'-3" X 72'-7" IRREGULAR SHAPED 1-STORY SFD W/ ADU PERGC 66323(a)(1) AND 2-CAR GARAGE. NPFA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/1/2025
Issuing Office
Valley
Current Status
Issued on 10/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/28/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 DANIEL ABRAMYAN
Corrections Issued 3/24/2025 DANIEL ABRAMYAN
Quality Review Completed 3/26/2025 OMID HEDAYAT
Building Plans Picked Up 4/2/2025 APPLICANT
Applicant returned to address corrections 9/9/2025 RAPHAEL ROSAS
Plan Check Approved 10/1/2025 RAPHAEL ROSAS
Issued 10/1/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/23/2025 COLIN LOREDO
Permit Cleared 5/23/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 5/23/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 5/27/2025 COLIN LOREDO
Sewer availability Cleared 5/27/2025 COLIN LOREDO
Disturb/Remove Protected Trees Cleared 8/7/2025 MIGUEL ORNELAS
Trees in Parkway Cleared 8/7/2025 MIGUEL ORNELAS
GPI Written Notices Cleared 9/9/2025 DANIEL ABRAMYAN
Grading Pre-Inspection Cleared 9/9/2025 DANIEL ABRAMYAN
Hydrant and Access approval Cleared 9/16/2025 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 5140 YOLANDA AVE      TARZANA, CA 91356

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/17/2026 Partial Approval ALEXANDER HANDY
Deputy Drilled-In Anchors 3/23/2026 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/25/2026 Approved ROBERT GOLD