13928 W TYLER ST 91342
Certificate Information: 13928 W TYLER ST 91342
- Application / Permit
- 25014-20000-00917
- Plan Check / Job No.
- B25VN05397
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* 29'-6" X 19'-6" ADDITION OF NEW ACCESSORY DWELLING UNIT ON SECOND FLOOR PER LAMC 12.22 A.33(c) and (d); (GARAGE AND STORAGE TO REMAIN)
- Permit Issued
- Issued on 12/16/2025
- Issuing Office
- Current Status
- Issued on 12/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2025 | SELLA BENYAMIN |
| Corrections Issued | 4/10/2025 | SELLA BENYAMIN |
| Quality Review Completed | 4/11/2025 | STEVEN KIM |
| Applicant returned to address corrections | 5/23/2025 | SELLA BENYAMIN |
| Applicant returned to address corrections | 6/5/2025 | SELLA BENYAMIN |
| Plan Check Approved | 7/1/2025 | SELLA BENYAMIN |
| Issued | 12/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/30/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/1/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 6/18/2025 | GEVORK KARAPETYAN |
| Roof/Waste drainage to street | Cleared | 6/21/2025 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/9/2026 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 1/15/2026 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2026 | Corrections Issued | KIRK SANDERS |
| Deputy Wood Construction | 2/17/2026 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 3/4/2026 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 3/4/2026 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 3/4/2026 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 3/4/2026 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 4/15/2026 | Approved | KEVIN BERBERYAN |
| Wood Frame | 4/15/2026 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/22/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/22/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/22/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/28/2026 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 4/28/2026 | Approved | KEVIN BERBERYAN |
| Insulation | 5/6/2026 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/6/2026 | Approved | KEVIN BERBERYAN |
| Shower Pan | 5/6/2026 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 5/11/2026 | Approved | KEVIN BERBERYAN |