7738 N WHITSETT AVE 91605

Certificate Information: 7738 N WHITSETT AVE 91605

Application / Permit
25014-20000-00916
Plan Check / Job No.
B25VN05393
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED ADDITION TO (E) DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1).
Permit Issued
Issued on 3/28/2025
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2025 APPLICANT
Assigned to Plan Check Engineer 3/5/2025 ARTIN ZARUKIAN
Corrections Issued 3/5/2025 ARTIN ZARUKIAN
Building Plans Picked Up 3/7/2025 APPLICANT
Plan Check Approved 3/28/2025 SARKIS HARABEDIAN
Issued 3/28/2025 APPLICANT
CofO in Progress 10/8/2025 MATTHEW NELSON
CofO Issued 11/13/2025 RUBEN SALAS
Permit Finaled 11/13/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/10/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/10/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/18/2025 BIAINA HARITUNIAN
Sewer availability Cleared 3/18/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 3/24/2025 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/4/2025 Partial Approval MATTHEW NELSON
Sewer 6/4/2025 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 6/11/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 7/8/2025 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/8/2025 Approved MATTHEW NELSON
Green Building Rough 7/8/2025 Not Ready for Inspection MATTHEW NELSON
MERV13>=Rough 7/8/2025 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 7/25/2025 Approved MATTHEW NELSON
Green Building Rough 7/25/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/25/2025 Partial Approval MATTHEW NELSON
MERV13>=Rough 7/25/2025 Approved MATTHEW NELSON
Rough-Elec/Plmb/HVAC 7/25/2025 Approved MATTHEW NELSON
Shower Pan 7/25/2025 Approved MATTHEW NELSON
Insulation 7/30/2025 Approved MATTHEW NELSON
Drywall Nailing 8/5/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 9/29/2025 Not Ready for Inspection MATTHEW NELSON
Final 9/29/2025 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 9/29/2025 Approved MATTHEW NELSON
Green Building Final 9/29/2025 Corrections Issued MATTHEW NELSON
HVAC-Final 9/29/2025 Corrections Issued MATTHEW NELSON
MERV13>=Final 9/29/2025 Approved MATTHEW NELSON
PLUMBING-Final 9/29/2025 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 9/29/2025 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 9/29/2025 Approved MATTHEW NELSON
Final 10/3/2025 Not Ready for Inspection DAVID ANDERSON
Green Building Final 10/3/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/3/2025 SGSOV Not Ready DAVID ANDERSON
Service/Power Release 10/3/2025 Not Ready for Inspection DAVID ANDERSON
Final 10/7/2025 OK to Issue CofO MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/7/2025 SGSOV Approved MATTHEW NELSON
Service/Power Release 10/17/2025 Approved DAVID ANDERSON