3768-3770 S MAY ST 90066

Certificate Information: 3768-3770 S MAY ST 90066

Application / Permit
25014-20000-00910
Plan Check / Job No.
B25VN05374
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO (E) SFD TO CONNECT THE SFD WITH RECREATION ROOM TO BE CONVERTED TO ACCESSORY DWELLING UNIT AND ADDITION TO ACCESSORY DWELLING UNIT AS PER LAMC 12.22 A.33 (c) and (e), ADDITION TO EXISTING ONE CAR GARAGE TO CONVERT TO A TWO CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/15/2025
Issuing Office
Current Status
CofO Issued on 2/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2025 APPLICANT
Assigned to Plan Check Engineer 3/6/2025 RARES BODEA
Corrections Issued 3/11/2025 RARES BODEA
Quality Review Completed 3/13/2025 STEVEN KIM
Building Plans Picked Up 3/14/2025 APPLICANT
Plan Check Approved 4/15/2025 RARES BODEA
Issued 4/15/2025 APPLICANT
CofO in Progress 2/12/2026 DAVID FEILER
Permit Finaled 2/17/2026 RICHARD STEINBACH
CofO Issued 2/17/2026 RICHARD STEINBACH
Permit Finaled 2/17/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/17/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 3/18/2025 DARIN LAM
Roof/Waste drainage to street Cleared 3/18/2025 DARIN LAM
Sewer availability Cleared 3/18/2025 DARIN LAM
Grading Pre-Inspection Cleared 3/26/2025 LANNY MERRICK
Specific Plan Cleared 4/1/2025 HAMID GHAEMMAGHAMI
Construction near power lines Cleared 4/7/2025 RIDWAN HARDY
GPI Written Notices Cleared 4/11/2025 RARES BODEA

Contact Information

Contractor Dolan Design & Build , Llc; Lic. No.: 1135363-B 1817 IOWA TRAIL      TOPANGA, CA 90290
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/8/2025 Corrections Issued MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 6/3/2025 Partial Approval MICHAEL ALLEN
Footing/Foundation/Slab 6/3/2025 Partial Approval MICHAEL ALLEN
Underground Mechanical 6/3/2025 Approved MICHAEL ALLEN
Deputy Drilled-In Anchors 6/9/2025 Partial Approval MICHAEL ALLEN
Footing/Foundation/Slab 6/11/2025 Approved JESUS RODRIGUEZ
Special/Order Compliance 6/11/2025 Partial Inspection JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 8/8/2025 Approved RUBEN RIVAS
HVAC-Rough 8/8/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 8/8/2025 Approved RUBEN RIVAS
Gas Test 8/13/2025 Approved WILBER ROSALES
HVAC-Rough 8/13/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 8/15/2025 Approved WILBER ROSALES
Green Building Rough 8/15/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 8/15/2025 Partial Approval WILBER ROSALES
Verify Sprinkler Sign Off 8/15/2025 Approved WILBER ROSALES
Insulation 8/27/2025 Approved WILBER ROSALES
Drywall Nailing 9/8/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 9/8/2025 Approved JAYLIN GRAVITTE
Shower Pan 9/8/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 1/27/2026 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 1/27/2026 Corrections Issued ANTHONY EGSON
PLUMBING-Final 1/27/2026 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 2/2/2026 Approved RUBEN RIVAS
Smoke Detectors 2/2/2026 Approved RUBEN RIVAS
Final 2/5/2026 Not Ready for Inspection ANTHONY EGSON
Gas Test 2/5/2026 Approved ANTHONY EGSON
Green Building Final 2/5/2026 Approved ANTHONY EGSON
HVAC-Final 2/5/2026 Approved ANTHONY EGSON
PLUMBING-Final 2/5/2026 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 2/5/2026 SGSOV Approved ANTHONY EGSON
Service/Power Release 2/5/2026 Not Ready for Inspection ANTHONY EGSON
Final 2/10/2026 OK to Issue CofO DAVID FEILER
Service/Power Release 2/10/2026 Approved DAVID FEILER