10263 W WOODBRIDGE ST 91602
Certificate Information: 10263 W WOODBRIDGE ST 91602
- Application / Permit
- 25014-20000-00894
- Plan Check / Job No.
- B25VN05260
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADDITION TO EXISTING ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(b). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 5/8/2025
- Issuing Office
- Current Status
- Issued on 5/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2025 | KAMYAR EMAMI |
| Corrections Issued | 3/10/2025 | KAMYAR EMAMI |
| Applicant returned to address corrections | 4/3/2025 | MADISON ODELL |
| Plan Check Approved | 4/23/2025 | KAMYAR EMAMI |
| Issued | 5/8/2025 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 3/12/2025 | DALIA MOKAYED |
| ZA Case | Cleared | 3/12/2025 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/22/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/4/2025 | CARLOS AGUILERA |
| ZI | Cleared | 4/8/2025 | DALIA MOKAYED |
| Hydrant and Access approval | Cleared | 4/21/2025 | KENNETH FRASER |
Contact Information
| Contractor | Sedano Builders Inc; Lic. No.: 1070321-B | , |
| Engineer | Guzman,, Martin; Lic. No.: C79193 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/3/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 10/3/2025 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 10/21/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2026 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/11/2026 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/18/2026 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/18/2026 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 3/18/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 3/18/2026 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/25/2026 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/14/2026 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 5/14/2026 | Corrections Issued | JAVIER RAMOS JR |
| Final | 5/14/2026 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 5/14/2026 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 5/14/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 5/14/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 5/14/2026 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 5/14/2026 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 5/14/2026 | Approved | JAVIER RAMOS JR |