18629 W BRYANT ST 91324

Certificate Information: 18629 W BRYANT ST 91324

Application / Permit
25014-20000-00882
Plan Check / Job No.
B25VN05162
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. CONVERT (E) DETACHED REC. ROOM INTO ADU AND ADDITION TO ADU TO BUILD A 963 SF ADU. PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 3/18/2025
Issuing Office
Current Status
Issued on 3/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/27/2025 APPLICANT
Assigned to Plan Check Engineer 3/3/2025 ALFREDO JARA
Corrections Issued 3/4/2025 ALFREDO JARA
Plan Check Approved 3/17/2025 ALFREDO JARA
Issued 3/18/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/7/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/11/2025 RYAN CASTRO
Sewer availability Cleared 3/11/2025 RYAN CASTRO
Miscellaneous Cleared 3/12/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 3/12/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Gonzalez,, Felix Bolivar; Lic. No.: NA64738       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2025 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 4/17/2025 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 4/21/2025 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Partial Inspection KRISTEN CAUSEY
Wood Frame 6/10/2025 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 6/23/2025 Approved KRISTEN CAUSEY
Green Building Rough 6/23/2025 Approved KRISTEN CAUSEY
Insulation 6/23/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 6/23/2025 Partial Approval KRISTEN CAUSEY
Drywall Nailing 7/11/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 7/11/2025 Not Ready for Inspection GEVORK IPCHYAN
Interior/Exterior Lathing 8/5/2025 Not Ready for Inspection KRISTEN CAUSEY
Shower Pan 8/5/2025 Approved KRISTEN CAUSEY
Final 10/6/2025 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 10/6/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 10/6/2025 SGSOV Not Ready ARUTYUN MADATYAN
Smoke Detectors 10/6/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 10/14/2025 Corrections Issued KRISTEN CAUSEY
Green Building Final 10/14/2025 Not Ready for Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 10/14/2025 Approved KRISTEN CAUSEY
Final 10/21/2025 Corrections Issued KRISTEN CAUSEY
Green Building Final 10/21/2025 Approved KRISTEN CAUSEY