Permit Issued
Issued on 3/27/2025
Issuing Office
Current Status
CofO Issued on 12/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2025 APPLICANT
Assigned to Plan Check Engineer 3/5/2025 JEROME MAGAT PALMA
Corrections Issued 3/5/2025 JEROME MAGAT PALMA
Building Plans Picked Up 3/21/2025 APPLICANT
Plan Check Approved 3/26/2025 MOHAMMAD ESMAILI
Issued 3/27/2025 APPLICANT
CofO in Progress 12/17/2025 JAVIER RAMOS JR
Permit Finaled 12/31/2025 RUBEN SALAS
CofO Issued 12/31/2025 RUBEN SALAS
Permit Finaled 12/31/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 3/13/2025 TINA MIRANDA
Specific Plan Cleared 3/14/2025 JOANNA MARROQUIN
Address approval Cleared 3/15/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/15/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/15/2025 LEE GUILBEAUX
Sewer availability Cleared 3/15/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/15/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/14/2025 Partial Inspection JAVIER RAMOS JR
Deputy Drilled-In Anchors 4/15/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 4/15/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 4/25/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 4/25/2025 Partial Approval JAVIER RAMOS JR
Sewer 4/25/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/18/2025 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 6/18/2025 Approved JAVIER RAMOS JR
HVAC-Rough 6/18/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/18/2025 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 6/18/2025 Approved JAVIER RAMOS JR
Shower Pan 6/18/2025 Approved JAVIER RAMOS JR
Drywall Nailing 7/8/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 10/23/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Final 10/23/2025 Corrections Issued JAVIER RAMOS JR
Final 10/23/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 10/23/2025 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 10/23/2025 Approved JAVIER RAMOS JR
HVAC-Final 10/23/2025 Corrections Issued JAVIER RAMOS JR
MERV13>=Final 10/23/2025 Approved JAVIER RAMOS JR
MERV13>=Rough 10/23/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 10/23/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/23/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 10/23/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 11/12/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Final 11/12/2025 Approved JAVIER RAMOS JR
Final 11/12/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 11/12/2025 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 11/12/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/17/2025 Approved JAVIER RAMOS JR
Drywall Nailing 12/17/2025 Approved JAVIER RAMOS JR
Final 12/17/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 12/17/2025 Approved JAVIER RAMOS JR
Insulation 12/17/2025 Approved JAVIER RAMOS JR