8235 N ALCOVE AVE 91605

Certificate Information: 8235 N ALCOVE AVE 91605

Application / Permit
25014-20000-00866
Plan Check / Job No.
B25VN05088
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN ADDITION TO AND CONVERT (E) DETACHED GARAGE INTO ADU PER GC66323(a)(2)
Permit Issued
Issued on 3/13/2025
Issuing Office
Current Status
CofO Issued on 12/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2025 APPLICANT
Assigned to Plan Check Engineer 3/3/2025 JOHNPAUL ISIP
Corrections Issued 3/4/2025 JOHNPAUL ISIP
Plan Check Approved 3/12/2025 JOHNPAUL ISIP
Issued 3/13/2025 APPLICANT
CofO in Progress 12/17/2025 VINCENT HANLEY
Permit Finaled 12/31/2025 RUBEN SALAS
CofO Issued 12/31/2025 RUBEN SALAS
Permit Finaled 12/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/8/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/8/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/8/2025 LEE GUILBEAUX
Sewer availability Cleared 3/8/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/8/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/26/2025 Partial Approval WILLIAM WREN
Sewer 3/28/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/1/2025 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 4/2/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/16/2025 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 4/28/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Approved VINCENT HANLEY
HVAC-Rough 4/28/2025 Approved VINCENT HANLEY
PLUMBING-Rough 4/28/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/2/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Approved VINCENT HANLEY
Green Building Rough 5/2/2025 Approved VINCENT HANLEY
MERV13>=Rough 5/2/2025 Approved VINCENT HANLEY
Insulation 5/7/2025 Approved VINCENT HANLEY
Drywall Nailing 5/23/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/10/2025 Approved VINCENT HANLEY
Shower Pan 6/10/2025 Approved VINCENT HANLEY
Final 11/7/2025 Not Ready for Inspection VINCENT HANLEY
Green Building Final 11/7/2025 Approved VINCENT HANLEY
MERV13>=Final 11/7/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV Not Required VINCENT HANLEY
Smoke Detectors 11/7/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 12/15/2025 Approved VINCENT HANLEY
Final 12/15/2025 Not Ready for Inspection VINCENT HANLEY
HVAC-Final 12/15/2025 Approved VINCENT HANLEY
PLUMBING-Final 12/15/2025 Approved VINCENT HANLEY
Final 12/16/2025 OK to Issue CofO VINCENT HANLEY