7207 W DOS RIOS DR 91042
Certificate Information: 7207 W DOS RIOS DR 91042
- Application / Permit
- 25014-20000-00862
- Plan Check / Job No.
- B25VN05053
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF A NEW BEDROOM TO THE (E) A.D.U. PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k) WITH NEW ATTACHED PATIO
- Permit Issued
- Issued on 3/4/2025
- Issuing Office
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2025 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/26/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/4/2025 | ALEC MOUSAKHANIAN |
| Issued | 3/4/2025 | APPLICANT |
| CofO in Progress | 7/2/2025 | WILLIAM WREN |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
| CofO Issued | 7/31/2025 | RUBEN SALAS |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/27/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/27/2025 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 2/27/2025 | CHARLES POWELL |
| Miscellaneous | Cleared | 3/4/2025 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 3/4/2025 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/18/2025 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 3/18/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 3/20/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 4/3/2025 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 4/3/2025 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Approved | WILLIAM WREN |
| Green Building Rough | 4/3/2025 | Approved | WILLIAM WREN |
| Insulation | 4/15/2025 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 4/15/2025 | Approved | WILLIAM WREN |
| Drywall Nailing | 4/23/2025 | Approved | WILLIAM WREN |
| Final | 5/29/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/29/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 5/29/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 5/29/2025 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 5/29/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 6/3/2025 | Not Ready for Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 6/3/2025 | Approved | WILLIAM WREN |
| Green Building Final | 6/3/2025 | Corrections Issued | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Not Required | WILLIAM WREN |
| Smoke Detectors | 6/3/2025 | Approved | WILLIAM WREN |
| Final | 6/24/2025 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 6/24/2025 | Approved | WILLIAM WREN |