8636 W EDWIN DR 90046

Certificate Information: 8636 W EDWIN DR 90046

Application / Permit
25014-20000-00847
Plan Check / Job No.
B25VN05006
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 573 SQ FT ON SECOND FLOOR; INTERIOR REMODEL TO DWELLING; ADD NEW 322 SQ FT GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 7/22/2025
Issuing Office
Current Status
Issued on 7/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/25/2025 APPLICANT
Assigned to Plan Check Engineer 2/27/2025 SELLA BENYAMIN
Corrections Issued 3/4/2025 SELLA BENYAMIN
Building Plans Picked Up 3/14/2025 APPLICANT
Quality Review Completed 7/22/2025 SELLA BENYAMIN
Plan Check Approved 7/22/2025 SELLA BENYAMIN
Issued 7/22/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/22/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 3/22/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 3/22/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 3/22/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/22/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/26/2025 CARLOS AGUILERA
Sewer availability Cleared 3/26/2025 CARLOS AGUILERA
Specific Plan Cleared 7/8/2025 TIFFANY CORRALES
GPI Written Notices Cleared 7/22/2025 SELLA BENYAMIN
Grading Pre-Inspection Cleared 7/22/2025 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/8/2025 Conditional Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 9/9/2025 Corrections Issued BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 9/11/2025 Approved ROY SPAULDING
Footing/Foundation/Slab 9/11/2025 Approved ROY SPAULDING
Deputy Reinf. Concrete 9/16/2025 Conditional Approval JOSH MEISTER
Deputy Steel/Welding 10/1/2025 Conditional Approval DAVID WILLIAMS
Underground Mechanical 10/1/2025 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/22/2025 Not Ready for Inspection ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Partial Approval DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 11/19/2025 Partial Approval ROY SPAULDING
Special/Order Compliance 12/9/2025 Partial Inspection ALEX COLIN
BUILDING-Rough-Frame 2/3/2026 Not Ready for Inspection DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Partial Approval DAVID WILLIAMS
Green Building Rough 2/3/2026 Approved DAVID WILLIAMS
PLUMBING-Rough 2/3/2026 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 2/3/2026 Not Ready for Inspection DAVID WILLIAMS
ELECTRICAL-Rough 2/4/2026 Corrections Issued ROY SPAULDING
HVAC-Rough 2/4/2026 Corrections Issued ROY SPAULDING
ELECTRICAL-Rough 2/9/2026 Not Ready for Inspection ROY SPAULDING
HVAC-Rough 2/9/2026 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 2/13/2026 Approved DAVID WILLIAMS
Shower Pan 2/13/2026 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 2/17/2026 Corrections Issued DAVID WILLIAMS
HVAC-Rough 2/17/2026 Not Ready for Inspection DAVID WILLIAMS
Interior/Exterior Lathing 2/17/2026 Not Ready for Inspection DAVID WILLIAMS
Verify Sprinkler Sign Off 2/17/2026 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 2/19/2026 Approved DAVID WILLIAMS
HVAC-Rough 2/19/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 2/19/2026 Partial Approval DAVID WILLIAMS
Interior/Exterior Lathing 3/11/2026 Approved DAVID WILLIAMS
Insulation 3/16/2026 Approved DAVID WILLIAMS
Drywall Nailing 3/24/2026 Approved DAVID WILLIAMS