11525 W HUSTON ST 91601

Certificate Information: 11525 W HUSTON ST 91601

Application / Permit
25014-20000-00841
Plan Check / Job No.
B25VN04983
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story addition and major remodel to an existing one-story single family dwelling.
Permit Issued
Issued on 3/11/2025
Issuing Office
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2025 APPLICANT
Assigned to Plan Check Engineer 2/28/2025 NGHI SU
Corrections Issued 3/2/2025 NGHI SU
Plan Check Approved 3/11/2025 CRYSTEL MAALOUF
Issued 3/11/2025 APPLICANT
CofO in Progress 1/21/2026 JAVIER RAMOS JR
Permit Finaled 3/10/2026 RUBEN SALAS
CofO Issued 3/10/2026 RUBEN SALAS
Permit Finaled 3/10/2026 RUBEN SALAS

Permit Application Clearance Information

Miscellaneous Cleared 3/3/2025 JOANNA MARROQUIN
Miscellaneous Cleared 3/3/2025 JOANNA MARROQUIN
ZI Cleared 3/3/2025 JOANNA MARROQUIN
ZI Cleared 3/3/2025 JOANNA MARROQUIN
Eng Process Fee Ord 176,300 Cleared 3/4/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 3/4/2025 SAFA JAVANMARDI
Sewer availability Cleared 3/4/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/20/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 3/21/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/1/2025 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 4/1/2025 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 No Access for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 4/7/2025 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/12/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 5/12/2025 Approved JAVIER RAMOS JR
Green Building Rough 5/12/2025 Approved JAVIER RAMOS JR
HVAC-Rough 5/12/2025 Approved JAVIER RAMOS JR
MERV13>=Rough 5/12/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 5/12/2025 Approved JAVIER RAMOS JR
Underground Mechanical 5/12/2025 Partial Approval JAVIER RAMOS JR
Insulation 5/29/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/29/2025 Corrections Issued JAVIER RAMOS JR
Shower Pan 5/29/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/2/2025 Partial Approval MICHAEL CORTEZ
Interior/Exterior Lathing 6/5/2025 Approved JAVIER RAMOS JR
Drywall Nailing 6/10/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 12/2/2025 Approved JAVIER RAMOS JR
Final 12/2/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 12/2/2025 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 12/2/2025 Approved JAVIER RAMOS JR
MERV13>=Final 12/2/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 12/2/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 12/2/2025 Approved JAVIER RAMOS JR
Final 1/21/2026 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 1/21/2026 Approved JAVIER RAMOS JR