7527 N CLAYBECK AVE 91505
Certificate Information: 7527 N CLAYBECK AVE 91505
- Application / Permit
- 25014-20000-00815
- Plan Check / Job No.
- B25VN04844
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/14/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 3/1/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/7/2025 | APPLICANT |
| Plan Check Approved | 3/13/2025 | KAMYAR EMAMI |
| Issued | 3/14/2025 | APPLICANT |
| CofO in Progress | 10/13/2025 | DAVID ANDERSON |
| CofO Issued | 12/18/2025 | RUBEN SALAS |
| Permit Finaled | 12/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 3/4/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 3/5/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/1/2025 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 4/2/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 4/2/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 4/3/2025 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 4/3/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Approved | DAVID ANDERSON |
| Green Building Rough | 4/9/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 4/23/2025 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 4/28/2025 | Corrections Issued | DAVID ANDERSON |
| Interior/Exterior Lathing | 4/28/2025 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 4/28/2025 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/6/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 5/6/2025 | Approved | DAVID ANDERSON |
| Green Building Rough | 5/6/2025 | Approved | DAVID ANDERSON |
| HVAC-Rough | 5/6/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 5/6/2025 | Approved | DAVID ANDERSON |
| Shower Pan | 5/6/2025 | Approved | DAVID ANDERSON |
| Insulation | 5/8/2025 | Approved | DAVID ANDERSON |
| Drywall Nailing | 5/14/2025 | Approved | DAVID ANDERSON |
| Sewer | 5/23/2025 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Final | 6/23/2025 | Corrections Issued | DAVID ANDERSON |
| Interior/Exterior Lathing | 6/23/2025 | Approved | DAVID ANDERSON |
| Service/Power Release | 6/23/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Underground Mechanical | 9/8/2025 | Partial Approval | DAVID ANDERSON |
| Service/Power Release | 9/19/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 10/6/2025 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 10/6/2025 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 10/6/2025 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 10/6/2025 | Approved | DAVID ANDERSON |
| Final | 10/10/2025 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Approved | DAVID ANDERSON |