11779 W SHELDON ST 91352
Certificate Information: 11779 W SHELDON ST 91352
- Application / Permit
- 25014-20000-00811
- Plan Check / Job No.
- B25VN04807
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- EPLAN. PROPOSED 2ND FLOOR OFFICE ADDITION TO (E) MANUFACTURING BUILDING. INSTALL CAR LIFTS.
- Permit Issued
- Issued on 12/3/2025
- Issuing Office
- Current Status
- Issued on 12/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2025 | RAPHAEL ROSAS |
| Assigned to Zoning Architect | 2/27/2025 | BENNY WONG |
| Corrections Issued | 3/6/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 3/12/2025 | STEVEN KIM |
| Applicant returned to address corrections | 4/22/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/8/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/9/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/27/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 11/24/2025 | RAPHAEL ROSAS |
| Issued | 12/3/2025 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 3/6/2025 | MARIA VENDIVIL |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/11/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/11/2025 | LEE GUILBEAUX |
| Green Code | Cleared | 5/6/2025 | MICHAEL AYERS |
| ZI | Cleared | 9/23/2025 | JACQUELINE TORRES |
| Mechanical Car Lift | Cleared | 10/21/2025 | FIRE DEPARTMENT |
| DAS Clearance | Cleared | 11/4/2025 | Crystel Maalouf |
| Zoning Plan Check | Cleared | 11/17/2025 | BENNY WONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: NA3141 | , |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/15/2026 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 4/15/2026 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 4/22/2026 | No Result Entered | ANDREW DORSO |