10116 W COLWELL DR 91352

Certificate Information: 10116 W COLWELL DR 91352

Application / Permit
25014-20000-00804
Plan Check / Job No.
B25VN04737
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO BEDROOM, BATHROOM, HALLWAY W/ LAUNDRY WITH 3'-11" x 17'-0" ADDITION AND (N) ATTACHED 19'-6" x 13'-6" PATIO COVER. ALL WORK PER WFPP.
Permit Issued
Issued on 3/13/2025
Issuing Office
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2025 APPLICANT
Assigned to Plan Check Engineer 2/27/2025 GIOVANNY CHAVEZ
Building Plans Picked Up 2/28/2025 APPLICANT
Plan Check Approved 3/13/2025 HAYATO TSUCHIYA
Issued 3/13/2025 APPLICANT
CofO in Progress 11/13/2025 DAVID ANDERSON
Permit Finaled 12/12/2025 RUBEN SALAS
CofO Issued 12/12/2025 RUBEN SALAS
Permit Finaled 12/12/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/5/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/10/2025 CARLOS AGUILERA
Sewer availability Cleared 3/10/2025 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/14/2025 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 4/16/2025 Approved DAVID ANDERSON
Footing/Foundation/Slab 4/16/2025 Approved DAVID ANDERSON
PLUMBING-Rough 4/24/2025 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 5/22/2025 Approved DAVID ANDERSON
Green Building Rough 5/22/2025 Approved DAVID ANDERSON
MERV13>=Rough 5/22/2025 Approved DAVID ANDERSON
Rough-Elec/Plmb/HVAC 5/22/2025 Approved DAVID ANDERSON
Shower Pan 5/22/2025 Approved DAVID ANDERSON
Wood Frame 5/28/2025 Approved DAVID ANDERSON
Insulation 6/3/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/3/2025 Partial Approval DAVID ANDERSON
Drywall Nailing 6/9/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 6/9/2025 Approved LOUIS ESCOTO
Final 10/28/2025 Corrections Issued DAVID ANDERSON
Green Building Final 10/28/2025 Approved DAVID ANDERSON
MERV13>=Final 10/28/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/28/2025 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 10/28/2025 Approved DAVID ANDERSON
Final 11/12/2025 OK to Issue CofO DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 11/12/2025 SGSOV Approved DAVID ANDERSON